5.13.
CC Regular Session
Meeting Date: 03/12/2024
   
Primary Strategic Plan Initiative: {ud_pd7}

Information

Title

Adopt Resolution #24-073 Approving Construction Contingency Expense No. 3 for Improvement Project #21-09, Centralized Water Treatment Plant

Purpose/Background:

Purpose:
The purpose of this case is to adopt Resolution #24-073 approving Construction Contingency Expense No. 3 for Improvement Project #21-09, Centralized Water Treatment Plant.  

Background:
The Water Treatment Plant (WTP) project includes a construction contingency cost of $950,000 intended to pay for new items during construction that were not contemplated during the design process or for items that the owner, engineer, or contractor(s) propose to revise during construction.

The attached letter from Construction Lead Ryan Hanson with Advanced Engineering and Environmental Services, Inc. (AE2S), the project engineer, identifies all items proposed to be adjusted during construction, including as part of Construction Contingency Expense No. 3.  The letter identifies all adjustments and all spent and remaining construction contingency funds to assist the City in better understanding the contingency status.  To date, AE2S has submitted ten (10) requests for pricing (RFP) to Magney Construction, the awarded WTP contractor, and has received pricing for nine (9) RFP’s. AE2S recommends approving Construction Contingency Expense No. 3 as summarized in the table below and the attached letter including Proposal No’s 010, 012, 013, 014, 015 and 016.  No time extensions are associated with these requests. 
 
Proposal No. RFP No. Description Total Cost Status
010 007 Backwash Supply Piping Modifications $3,068.77 Pending
012   Accordion Folding Security Door $10,010.85 Pending
013 008 Jet Mixing System Pump Modifications $16,834.33 Pending
014 009 Backwash Tank Overflow $1,534.38 Pending
015   Field Order No. 4 - Door Hardware Changes $10,922.45 Pending
016   Door Hardware Changes $56,724.85 Pending

As construction progresses, AE2S will continue to provide cost updates, coordinate closely with the City on all issues impacting project costs, support and track the progress of the WTP, and provide updates as needed so the City can make responsible decisions on the progress of the WTP.  
 

Notification:

Notifications are not required for this case.   

Observations/Alternatives:

Alternative #1:
Motion to adopt Resolution #24-073 approving Construction Contingency Expense No. 3 for Improvement Project #21-09, Centralized Water Treatment Plant.   

 

Funding Source:

The attached letter and supporting documentation identify project cost impacts related to Construction Contingency Expense No. 3, which totals $99,095.63.  The original Construction Contingency amount was $950,000.  Approving Construction Contingency Expense No. 3 will reduce the available construction contingency amount to $638,803.82.   

Recommendation:

Staff and AE2S recommend approving Alternative #1.  

Action:

Motion to adopt Resolution #24-073 approving Construction Contingency Expense No. 3 for Improvement Project #21-09, Centralized Water Treatment Plant.  

Attachments

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 03/06/2024 01:20 PM
Form Started By:
Bruce Westby
Started On:
03/04/2024 12:54 PM
Final Approval Date:
03/06/2024