Skip to main content

AgendaQuick™

View Agenda Item

5.3.
Public Works Committee
Meeting Date: 04/16/2024
   
Primary Strategic Plan Initiative: {ud_pd8}

Title:

Consider recommending City Council approving plans and specifications and authorizing advertisement for bids for 2024 Neighborhood Pavement Overlay Improvements, Improvement Project #24-07

Purpose/Background:

Purpose:
The purpose of this case is to consider recommending City Council approving plans and specifications and authorizing advertisement for bids for 2024 Neighborhood Pavement Overlay Improvements, Improvement Project #24-07.
 
Background:
The proposed 2024 – 2033 Capital Improvement Program (CIP) identifies seven (7) subdivisions for pavement overlay improvements in 2024. Street segment summaries are attached to this case.
 
Project History
  • August 8, 2023, Resolution #23-182, the Ramsey City Council executed a proposal from Braun Intertec to prepare a pavement core analysis of Bowers Drive.
  • November 14, 2023, Resolution #23-281, the Ramsey City Council executed a proposal from Bolton and Menk to perform a topographic survey of the pedestrian ramps within the project area.
  • November 21, 2023, the Ramsey Public Works Committee considered recommending City Council order plans and specifications, additionally discussed constructing the gravel section of Basalt Street as part of these improvements.
  • November 28, 2023, Resolution #23-299, the Ramsey City Council ordered plans and specifications for 2024 Neighborhood Pavement Overlays, Improvement Project #24-07.
  • February 2, 2024, the Ramsey Public Works Committee considered adding a trail connection between Bowers Drive and the Riverstone South subdivision.
  • March 26, 2024, the Ramsey City Council reviewed the trail connection resident survey at the Work Session, recommending to not move forward with the connection.
 
The projects total approximately 4.32 miles in length, with varying mill thicknesses proposed. The project areas include:
 
  • Alpine Acres 1st & 2nd
    • Generally located east of Sunfish Lake Blvd and north of Alpine Drive
      • Residential townhouse subdivision
      • Construction in 2004
        • 0.85 miles of 32’ wide urban section with concrete curb & gutter
      • Crack seal / seal coat improvements in 2009 and 2016
      • Crack seal improvement in 2023
    • Subdivision was prioritized due to pavement stripping
 
  • Bowers Mississippi Acres 1st, 2nd, & 3rd
    • Generally located south of Riverdale Drive and 148th Avenue
      • Residential single-family house subdivision
      • Construction in 1982
        • 0.99 miles of mix 24’ wide urban section with bituminous curbing and rural section with drainage swales adjacent to roadway
      • Crack seal / seal coat improvement in 1996
      • Overlay improvement in 2004
      • Crack seal / seal coat improvements in 2009 and 2016
    • Subdivision was prioritized due to concerns pavement conditions falling beyond scope of pavement overlay improvement
 
  • Gateway Industrial Park 2nd and Ebony Addition
    • Generally located southwest of Bunker Lake Blvd and Sunfish Lake Blvd
      • Commercial / Industrial subdivision
      • Constructed between 1991 and 2007
        • 0.49 miles of 38’ wide urban section with concrete curb and gutter
      • Crack seal / seal coat improvements in 2003, 2012 and 2017
 
  • Section 27 Unplatted
    • Generally located southwest of Bunker Lake Blvd and Sunfish Lake Blvd
      • Commercial / Industrial subdivision
      • Constructed in 2001
        • 0.47 miles of 40’ wide urban section with concrete curb and gutter
      • Crack seal / seal coat improvements in 2006 and 2018
 
  • Orchard Hills Townhomes
    • Generally located south of Alpine Drive and east of TH 47
      • Residential townhouse subdivision
      • Construction in 2001
        • 0.30 miles of 32’ wide urban section with concrete curb & gutter
      • Crack seal / seal coat improvements in 2006 and 2013
      • Crack seal improvement in 2021
 
  • Seasons of Ramsey
    • Generally located north of Bunker Lake Blvd, east of Center Street
      • Residential single-family and townhouse subdivision
      • Construction in 2013
        • 0.08 miles of 31’ wide urban section with concrete curb & gutter
      • Subdivision was prioritized due to pavement condition and project location
        • Street patching due to Garden View development service connections
        • Development contributed funds towards overlay improvements
 
  • Town Center Gardens 1st, 2nd, & 3rd
    • Generally located north of Bunker Lake Blvd, west of Ramsey Blvd
      • Residential townhouse subdivision
      • Construction between 2004 and 2005
        • 1.14 miles of 32’ wide urban section with concrete curb & gutter
      • Crack seal / seal coat improvement in 2010
      • Crack seal improvement in 2021
 
Proposed Improvements
Review of ground penetrating radar (GPR), as-built plans, and the Bowers Drive Mill and Overlay Evaluation performed by Braun Intertec indicates three separate mill and overlay thicknesses will be used on the various street segments.
 
Orchard Hills Townhomes subdivision does not have sufficient pavement thickness for a 2-inch mill and overlay improvements, therefore a 1.0-inch mill and 1.5-inch bituminous overlay will be used. The section of Cobalt Street between Alpine Drive and 152nd Lane is proposed to receive a full-depth mill and fill of approximately 3.5-inches.
 
Bowers Drive will receive a full-depth mill and overlay of approximately 3.5-inches. The bituminous will be placed in 2 lifts.  Additionally, some minor base corrections are anticipated to be required.
 
All remaining subdivisions have sufficient existing bituminous thickness to perform a 2-inch mill and bituminous overlay.
 
Per typical overlay improvements, spot concrete curb and gutter repairs will be performed on damaged curb. Where feasible, the City has switched to a saw & seal method for curb cracks at a significant cost savings. This is performed on hairline cracks, without vertical displacement. For areas of bituminous curbing, repairs to the curbing are not anticipated, though the City typically updates curb adjacent to storm sewer inlets to concrete during mill and overlay projects.
 
Municipal sewer and water exist under all street segments in the project except for Bowers Drive. This project is not proposing any repairs to watermain or sanitary sewer.
 
Minor storm sewer structure repairs, typically re-grouting catch basins, is proposed. Additionally, the project proposes adding hydrodynamic separators to the storm sewer system along Bowers Drive for the two outlets to the Mississippi River. The separators are a cost-effective TSS removal device, which is used in leu of infiltration basins. Infiltration basins would require significant surface area, grading, and drainage easements which the City do not currently have.
 
Four of the townhouse subdivisions include extensive pedestrian ramps which do not meet current American with Disability Act (ADA) standards, and will require upgrades. A total of 50 pedestrian ramps were found to require upgrades, and will be replaced during construction.
 
As an alternative bid item, this project also includes constructing the gravel segment of Basalt Street south of 141st Avenue to a fulling paved street section including concrete curb and gutter. The street will be built to a width of 36 feet, with parking on one side, and terminate in a cul-de-ac built to 66 feet in diameter. This is the largest cul-de-sac which will fit in the existing right of way. Staff reviewed options for increasing the cul-de-sac to the standard 100-foot diameter, but found it not feasible, largely due to the significant impacts on the existing commercial adjacent to the street. The pavement will be built to a 10-ton pavement strength design which is typical for industrial streets, this will be achieved by placing 4-inches bituminous on top of 6-inches aggregate base.
 
Preliminary Schedule Remaining
  • Council approves plans and specifications / authorizes advertisement for bids
    • April 23, 2024
  • Staff receives bids
    • June 3, 2024
  • Council awards contract to the lowest responsible bidder
    • June 11, 2024
  • Contractor begins construction
    • July 2024
  • Substantial Completion
    • August 31, 2024
  • Final Completion
    • September 30, 2024
 
Full plans are not attached to this case to prevent potential bidders from downloading plans attached to the case to prepare and submit their bids, rather than purchasing the plans through QuestCDN, the electronic bidding software used by the City of Ramsey. This ensures all bidders are bidding off the same set of plans, and all bidders are notified of any plan revisions (addenda) issued during the bidding process. Attached is the plan sheet showing the typical sections, which includes information on the proposed pavement sections. Plans are available upon request from the City Engineer.

Notification:

Notification is not required for this case.

Time Frame/Observations/Alternatives:

Timeframe:
Staff anticipates this case will take approximately 15 minutes to present and respond to questions.
 
Observations:
The Basalt Street construction is proposed to be bid as an alternate.
 
Alternatives:
Alternative #1: Motion to recommend City Council approve plans and specifications and authorize advertisement for bids for 2024 Neighborhood Pavement Overlay Improvements, Improvement Project #24-07.
 
Alternative #2: Motion of other.

Funding Source:

Funding for this improvement is proposed to come from Pavement Management (PM) Funds, Stormwater Utility Funds and Sanitary Sewer Utility Funds. The alternative Basalt Street construction does not qualify for Pavement Management Funds, funding would likely be Public Improvement Revolving (PIR) Funds.
 
The City collected a $10,000 Road Improvement Fee as part of the Garden View development in 2019, to be used towards a future pavement mill and overlay of 147th Lane (Seasons of Ramsey segment). This was due to the significant street patches within 147th Lane required for water and sewer connections as part of the development.
 
The estimated costs below include 14-percent indirect costs for administrative, engineering, finance, and legal costs.
 
  • Base Street project costs                     $1,452,946.74
  • Alt Bid Street project costs                 $93,264.28
    • Basalt Street
  • Base Stormwater project costs            $146,068.20
  • Base Sanitary Sewer project costs      $6,156.00
  • Alt Bid Sanitary Sewer project costs  $570.00
    • Basalt Street
  • Total Project Costs                           $1,699,005.22

Recommendation:

Staff recommends alternative #1.

Outcome/Action:

Motion to recommend City Council approve plans and specifications and authorize advertisement for bids for 2024 Neighborhood Pavement Overlay Improvements, Improvement Project #24-07.

Attachments

Form Review

Inbox Reviewed By Date
Bruce Westby Bruce Westby 04/10/2024 04:04 PM
Brian Hagen Brian Hagen 04/10/2024 08:54 PM
Form Started By:
Joe Feriancek
Started On:
04/05/2024 03:30 PM
Final Approval Date:
04/10/2024