Receive Updates on Improvement Projects, Studies and Items of Interest

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions
  • Contract executed
  • Preconstruction meeting April 15, 2024
  • Construction proposed for Spring/Summer 2024
#24-02 Halls Dover Acres Street Reconstruction
  • Contract executed
  • Preconstruction meeting April 15, 2024
  • Construction proposed for Spring/Summer 2024
#24-03 2024 NE Ramsey Street Reconstruction
  • See separate PWC case
#24-04 Ford Brook Estates Drainage Improvements
  • Finalizing design and coordination with property owners, City of Nowthen and MnDOT
  • Anticipate requesting CC approval to advertise bids May 14, 2024
#24-05 Xkimo St MSA (TH47 to 142nd Avenue) Reconstruction
  • Bid opening May 8, 2024
#24-06 2024 MSA Pavement Overlay Improvements (McKinley St)
  • Plan preparation in progress
#24-07 2024 Neighborhood Overlay Improvements
  • See separate PWC case
#24-08 2024 Crack Seal Improvements
  • Contract executed
  • Construction proposed for Summer 2024
#24-09 2024 Pavement Rejuvenator Improvements
  • See separate PWC case
#24-10 2024 MSA Pavement Markings
  • See separate PWC case
#24-11 Alpine Drive MSA Street Reconstruction (Puma St to CSAH 83)
  • Contracts are being executed
  • Construction proposed for Spring/Summer 2024
#24-12 Juniper Woods 1st – 3rd Street Reconstruction
  • Contract executed
  • Preconstruction meeting April 15, 2024
  • Construction proposed for Spring/Summer 2024
#24-51 TH 47 Trail Gap Connection – 142nd Avenue to Xkimo Street
  • Bolton & Menk preparing plans and specs for 10’ trail construction
  • Request for Quotes anticipated Spring 2024
#23-01 161st Avenue Reconstruction
  • Final payment anticipated Spring 2024
#23-02 Central Park Parking Lot Reconstruction
  • Final payment anticipated Spring 2024
#23-04 167th Avenue Reconstruction
  • Final payment anticipated Spring 2024
#23-05 Barthels Rum River Acres 2nd Reconstruction
  • Final payment anticipated Spring 2024
#23-10 Whispering Pines Estates Plat 3 Reconstructions
  • Final payment anticipated Spring 2024
#23-19 COR Infrastructure Improvements
  • Construction in progress
  • Construction completion anticipated August 2024
#23-20 COR Mass Grading
  • Substantially complete
  • Working to correct leaks in pond lining
  • Final completion anticipated Spring 2024
#22-17 Highway 47 Sound Wall north of Xkimo Street
  • See separate PWC case
#21-08 WTP Trunk Watermain Improvements
  • Construction in progress
  • Includes reconstruction of 143rd Avenue
#21-09 Centralized Water Treatment Plant
  • Construction on schedule for substantial completion May 1, 2025
  • Final completion scheduled for August 1, 2025
#20-11 Ramsey Gateway Highway 10 Improvements  
City of Anoka Improvement Projects
Highway 47 Corridor Improvements
  • 3-lane design proposed south of Bunker Lake Boulevard
  • City received regional solicitation funds for 2027 construction
  • Signal system at McKinley Street proposed to be permanent
  • Anoka webpage https://clients.bolton-menk.com/anokahwy47/
 
Anoka County Improvement Projects
2024 Pavement Overlay Improvements
  • Portions of CSAH 83 and CR 27 will receive pavement overlays in 2024
  • Staff reviewed plans and City Engineer signed title sheet for CSAH 83 plans
 
MnDOT Improvement Projects
Anoka Solution Highway 10 Improvements
  • Final completion Spring 2024
US 10 / 169 & Ferry Street / TH 47 Interchange
  • Final completion Spring 2024
Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing  
Studies & Items of Interest
YIELD sign request for merge lane from EB CR 5 to SB Hwy 47
  • MnDOT investigated the City’s request and will not be adding yield signs.  
Commercial/Industrial/Residential Developments
  • Staff can respond to questions as needed.  

Notification:

Notifications are not required for this case. 

Time Frame/Observations/Alternatives:

Staff estimates up to 10 minutes will be needed for updates and discussion. 

Recommendation:

Staff will offer recommendations on specific items when requested. 

Outcome/Action:

No formal action required.  For Committee review and discussion purposes only. 

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Brian Hagen Marsha Weidner 04/11/2024 01:31 PM
Form Started By:
Bruce Westby
Started On:
04/10/2024 04:43 PM
Final Approval Date:
04/11/2024