Title:
Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
he purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions
City of Anoka Improvement Projects
Highway 47 Corridor Improvements
Anoka County Improvement Projects
2024 Pavement Overlay Improvements
MnDOT Improvement Projects
Anoka Solution Highway 10 Improvements
Studies & Items of Interest
Commercial/Industrial/Residential Developments
City Improvement Projects
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions
- Construction in progress
- Numerous clay pockets have been found that must be hauled out and replaced with suitable fill
- Substantial completion scheduled for Summer/Fall 2024
- Construction starting soon
- Substantial completion scheduled for Summer/Fall 2024
- Bids publicly opened May 20th
- City Council will consider awarding a construction contract May 28th
- Staff applied for MnDOT Right-of-Way permit for Highway 47
- City Council will consider approving plans and advertising bids on May 28th
- Executing contract documents and scheduling preconstruction meeting
- Construction proposed for Spring/Summer 2024
- Plan preparation in progress
- Construction proposed for Summer/Fall 2024
- Bids will be publicly opened June 4th
- Construction proposed for Spring/Summer 2024
- Construction complete by May 31st
- Bids publicly opened May 20th
- City Council will consider awarding a construction contract May 28th
- Bids publicly opened May 20th
- City Council will consider awarding a construction contract May 28th
- Preconstruction meeting was conducted May 17th
- Construction proposed for Spring/Summer 2024
- Construction in progress
- Substantial completion scheduled for Summer/Fall 2024
- Bolton & Menk preparing plans and specs for 10’ trail construction
- Request for Quotes anticipated Spring 2024
- Final payment anticipated Spring 2024
- Final payment anticipated Spring 2024
- Final payment anticipated Spring 2024
- Final payment anticipated Spring 2024
- Final payment anticipated Spring 2024
- Construction in progress
- Construction completion anticipated August 2024
- Working to correct leaks in pond lining
- Final completion anticipated Spring 2024
- City Council will consider approving plans and CCA and authorizing bids May 28th
- Construction proposed for Summer 2024 with substantial completion on August 31st
- Construction in progress
- Reconstruction of 143rd Avenue proposed to start late May/early June
- Construction on schedule for substantial completion May 1, 2025
- Final completion scheduled for August 1, 2025
- Construction in progress
- Final completion anticipated June 2026
- Project webpage https://www.anokacountymn.gov/3918/Hwy-10Ramsey-Blvd-Interchange
City of Anoka Improvement Projects
Highway 47 Corridor Improvements
- 3-lane design proposed south of Bunker Lake Boulevard
- City received regional solicitation funds for 2027 construction
- Signal system at McKinley Street proposed to be permanent
- Anoka webpage https://clients.bolton-menk.com/anokahwy47/
Anoka County Improvement Projects
2024 Pavement Overlay Improvements
- Portions of CSAH 83 and CR 27 will receive pavement overlays in 2024
- Staff reviewed plans and City Engineer signed title sheet for CSAH 83 plans
MnDOT Improvement Projects
Anoka Solution Highway 10 Improvements
- Final completion Spring 2024
- Final completion Spring 2024
- Preliminary design officially paused to explore S-curve realignment and stormwater impacts
- $45M in bonds authorized October 2020
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy47rr-anoka/
Studies & Items of Interest
Commercial/Industrial/Residential Developments
- Staff can respond to questions as needed.
Time Frame/Observations/Alternatives:
Staff estimates up to 10 minutes will be needed for updates and discussion.
Recommendation:
Staff will offer recommendations on specific items when requested.
Outcome/Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 05/16/2024 12:04 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 05/15/2024 04:29 PM
- Final Approval Date:
- 05/16/2024