Receive Updates on Improvement Projects, Studies and Items of Interest

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
#25-01 Rivers Bend Regional Stormwater Pond Improvements
  • Advertisements for bids are published
  • Bid opening September 6, 2024  
  • Staff is applying for additional external funding
  • Substantial completion scheduled for November 22, 2024
#25-02 MSA Sunwood Drive Reconstruction – CSAH 5 to Erkium Street
  • Design and plan preparation in progress
  • 2025 construction
#25-03 MSA Alpine Drive Reconstruction – CSAH 57 to TH 47
  • Design and plan preparation in progress
  • 2025 construction
#24-01 Barthel’s Rum River Acres & White Pine Estates Street Reconstructions
  • Construction in progress
  • Substantial completion scheduled for August 2, 2024
#24-02 Halls Dover Acres Street Reconstruction
  • Construction in progress
  • Substantial completion scheduled for August 2, 2024
#24-03 2024 NE Ramsey Street Reconstruction
  • Construction in progress 
  • Substantial completion scheduled for September 30, 2024
#24-04 Ford Brook Estates Drainage Improvements
  • Construction anticipated to start mid-September
  • Substantial completion anticipated October 25, 2024
#24-05 Xkimo St MSA (TH47 to 142nd Avenue) Reconstruction
  • Construction in progress.
  • Substantial completion scheduled for September 1, 2024
#24-06 2024 MSA Pavement Overlay Improvements (McKinley St)
  • Executing contracts  
  • Substantial completion scheduled for October 11, 2024
  • Final completion scheduled for June 30, 2025
#24-07 2024 Neighborhood Overlay Improvements
  • Construction in progress
  • Substantial completion scheduled for August 31, 2024
#24-09 2024 Pavement Rejuvenator Improvements
  • Construction in progress
  • Final completion is anticipated to occur by August 30, 2024
#24-10 2024 MSA Pavement Markings
  • Substantially complete 
#24-11 Alpine Drive MSA Street Reconstruction (Puma St to CSAH 83)
  • Substantially complete
#24-12 Juniper Woods 1st – 3rd Street Reconstruction
  • Substantially complete
#24-51 TH 47 Trail Gap Connection – 142nd Avenue to Xkimo Street
  • Bolton & Menk preparing plans and specs for 10’ trail construction
  • Request for Quotes anticipated soon
#23-19 COR Infrastructure Improvements
  • Construction in progress
  • Construction completion anticipated late August 2024
#23-20 COR Mass Grading
  • Final completion anticipated late August 2024
#22-17 Highway 47 Sound Wall north of Xkimo Street
  • Final construction complete
#21-08 WTP Trunk Watermain Improvements
  • Construction in progress
  • 143rd Avenue restricted to one-way traffic (Westbound only)
  • Substantial completion anticipated September 13, 2024
#21-09 Centralized Water Treatment Plant
  • Construction in progress
  • Substantial completion scheduled for May 1, 2025
  • Final completion scheduled for August 1, 2025
#20-11 Ramsey Gateway Highway 10 Improvements  
City of Anoka Improvement Projects
Ferry Street / Turnk Highway 47 Grade Separation of BNSF Rail Crossing
  • City of Anoka assuming lead role
  • $45M in bonds authorized October 2020
Highway 47 Corridor Improvements – Garfield St to Bunker Lk Blvd
  • Combining with above as one City-led project
  • 3-lane design
  • Received regional solicitation funds for 2027 construction
  • Signal system at McKinley Street
  • See attached flyer
  • Construction proposed for 2027 - 2029
 
Anoka County Improvement Projects
2024 Pavement Overlay Improvements  
MnDOT Improvement Projects
N/A
  

Studies & Items of Interest
Wetland 114 P staff updates
  • Water levels have stabilized
  • Staff will provide a verbal update during the meeting.
Commercial/Industrial/Residential Developments
  • Staff can respond to questions as needed. 
 
PWC Future Topics Calendar Discussion Items
No updates.   

Time Frame/Observations/Alternatives:

Staff estimates up to 15 minutes will be needed for updates and discussion.  

Recommendation:

Staff will offer recommendations on specific items when requested.  

Outcome/Action:

No formal action required.  For Committee review and discussion purposes only.  

Attachments

Form Review

Inbox Reviewed By Date
Brian Hagen Marsha Weidner 08/16/2024 03:22 PM
Form Started By:
Bruce Westby
Started On:
08/12/2024 03:28 PM
Final Approval Date:
08/16/2024