6.15.
| CC Regular Session |
| Meeting Date: | 10/22/2024 |
| Primary Strategic Plan Initiative: | {ud_pd4} |
Title:
Adopt Resolution #24-301 Approving Partial Payment to Douglas-Kerr Undergroun, LLC. for Improvement Project #23-19, The COR Infrastructure Improvements.
Purpose/Background:
Resolution and Pay Request Attached.
Recommendation:
The Senior Engineering Technician has inspected the completed work and recommends partial payment to Douglas-Kerr Underground, LLC. for improvement project #23-169, The COR Infrastructure Improvements, in the amount of $30,172.24.
Outcome/Action:
Motion to adopt Resolution #24-301 approving partial payment to Douglas-Kerr Underground, LLC. for improvement project #23-19, The COR Infrastructure Improvements, in the amount of $30,172.24.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Stacie Damjanovich | 10/16/2024 11:21 AM |
| Bruce Westby | Bruce Westby | 10/17/2024 01:17 PM |
| Brian Hagen | Brian Hagen | 10/17/2024 02:25 PM |
- Form Started By:
- Stacie Damjanovich
- Started On:
- 10/11/2024 10:59 AM
- Final Approval Date:
- 10/17/2024