6.15.
| CC Regular Session |
| Meeting Date: | 12/10/2024 |
| Primary Strategic Plan Initiative: | {ud_pd4} |
Title:
Adopt Resolution #24-360 Approving Partial Payment to Northdale Construction Co. Inc. for Improvement Project #21-08, WTP Trunk Watermain Improvements.
Purpose/Background:
Resolution and Pay Request Attached.
Recommendation:
The Senior Engineering Technician has inspected the completed work and recommends partial payment to Northdale Construction Co. Inc. for improvement project #21-08, WTP Trunk Watermain Improvements in the amount of $296,261.34.
Outcome/Action:
Motion to adopt Resolution #24-360 approving partial payment to Northdale Construction Co. Inc. for improvement project #21-08, WTP Trunk Watermain Improvements in the amount of $296,261.34.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 12/05/2024 01:48 PM |
| Brian Hagen | Brian Hagen | 12/05/2024 03:04 PM |
- Form Started By:
- Stacie Damjanovich
- Started On:
- 12/03/2024 10:10 AM
- Final Approval Date:
- 12/05/2024