6.2.
| Public Works Committee |
| Meeting Date: | 03/18/2025 |
| Primary Strategic Plan Initiative: | {ud_pd8} |
Title:
Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
2026 Pavement Management Program Projects
City of Anoka Improvement Projects
Ferry Street/Trunk Highway 47 Grade Separation of BNSF Rail Crossing
Anoka County Improvement Projects
MnDOT Improvement Projects
Studies & Items of Interest
Wetland 114 P staff updates
PWC Future Topics Calendar Discussion Items
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
2026 Pavement Management Program Projects
- Soliciting RFPs for topographic surveys, geotechnical evaluations and utility testing
- Construction complete
- Received first grant payment from Anoka Conservation District (ACD) of $168,874.49
- Second grant payment invoice submitted on 3/12/25 for $156,675.51
- Project close out scheduled for Spring 2025
- Contract awarded to North Valley, Inc. for $272,962.90
- Scheduling preconstruction meeting
- 2025 construction
- 2025 construction
- See separate case
- 2025 construction
- Bids advertised
- 2025 construction
- Bids advertised
- 2025 construction
- Contract awarded to FlowSeal Surface Maintenance for $154,749.49
- 2025 construction
- Contract awarded to Corrective Asphalt Materials, LLC for $233,191.32
- 2025 construction
- 2025 construction proposed per CIP
- PWC case proposed for April 15th
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Final completion scheduled for June 30, 2025
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Contract awarded to Douglas-Kerr Underground, LLC for $2,099,737.06
- Preconstruction meeting Monday, March 24th
- 2025 construction
- 2025 Change Order to IP #20-11, Ramsey Gateway Highway 10 Improvements
- Bolton & Menk prepared plans and specs for 10’ trail construction
- PWC case on MnDOT cost contribution update anticipated for April 15th
- Construction complete
- Punch list items are being addressed
- Construction complete
- Final payment in progress
- Construction in progress
- Substantial completion August, 2025
- Final completion October, 2025
- Sunfish Lake Blvd grade separations (RR and TH10) substantially complete
- Ramsey Blvd grade separations (RR and TH10) heavy construction starts in March 2025
- Final completion anticipated June 2026
- Project webpage https://www.anokacountymn.gov/3918/Hwy-10Ramsey-Blvd-Interchange
City of Anoka Improvement Projects
Ferry Street/Trunk Highway 47 Grade Separation of BNSF Rail Crossing
- City-led project
- $45M in bonds authorized October 2020
- 2028 construction anticipated
- Combined with above City-led project
- 3-lane design
- Received regional solicitation funds for 2027 construction
- Permanent signal system at McKinley Street
- Construction proposed for 2027 - 2029
Anoka County Improvement Projects
- No updates.
MnDOT Improvement Projects
- No updates.
Studies & Items of Interest
Wetland 114 P staff updates
- Staff continue to monitor water levels and will provide updates as needed.
- Staff can respond to questions as needed.
PWC Future Topics Calendar Discussion Items
- See calendar in the next case.
Notification:
Notification is not required for this case.
Time Frame/Observations/Alternatives:
Staff estimates up to 10 minutes will be needed for updates and discussion.
Recommendation:
Staff will offer recommendations on specific items when requested.
Outcome/Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 03/13/2025 12:45 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 02/28/2025 02:14 PM
- Final Approval Date:
- 03/13/2025