5.17.
| CC Regular Session |
| Meeting Date: | 05/13/2025 |
| Primary Strategic Plan Initiative: | {ud_pd8} |
Title:
Adopt Resolution #25-102 Awarding Construction Staking Contract for High Point Street Reconstructions, Improvement Project #25-05
Purpose/Background:
Purpose:
The purpose of this case is to adopt Resolution #25-102 awarding construction staking contract for High Point Street Reconstructions, Improvement Project #25-05.
Background:
On April 22, 2025, City Council adopted Resolution #25-071, awarding a construction contract to North Valley, Inc. for the High Point Street Reconstructions, Improvement Project #25-05.
Construction staking is essential to the construction of said improvements, and City Staff does not have the capacity to perform construction staking in-house.
Hakanson Anderson submitted a proposal for construction staking and as-built survey of the proposed improvements for a total amount of $28,800.00.
City Staff proposes to administer and inspect construction. Plans and specifications were prepared in-house as part of Staff’s normal duties.
The purpose of this case is to adopt Resolution #25-102 awarding construction staking contract for High Point Street Reconstructions, Improvement Project #25-05.
Background:
On April 22, 2025, City Council adopted Resolution #25-071, awarding a construction contract to North Valley, Inc. for the High Point Street Reconstructions, Improvement Project #25-05.
Construction staking is essential to the construction of said improvements, and City Staff does not have the capacity to perform construction staking in-house.
Hakanson Anderson submitted a proposal for construction staking and as-built survey of the proposed improvements for a total amount of $28,800.00.
City Staff proposes to administer and inspect construction. Plans and specifications were prepared in-house as part of Staff’s normal duties.
Notification:
Notifications are not required as part of this case.
Time Frame/Observations/Alternatives:
Adopt Resolution #25-102 awarding construction staking contract for High Point Street Reconstructions, Improvement Project #25-05.
Funding Source:
On April 22, 2025, City Council adopted Resolution #25-071 awarding a construction contract to North Valley, Inc. for the High Point Street Reconstructions, Improvement Project #25-05, in the bid amount of $1,366,954.38. Adding indirect costs in the amount of 23-percent, the total project costs are $1,681,353.89.
Hakanson Anderson submitted a proposal for construction staking and as-built survey of the proposed improvements for a total amount of $28,800.00. These services are included in the indirect project costs and are proposed to be paid for with Pavement Management Funds and Storm Sewer Utility Funds.
Hakanson Anderson submitted a proposal for construction staking and as-built survey of the proposed improvements for a total amount of $28,800.00. These services are included in the indirect project costs and are proposed to be paid for with Pavement Management Funds and Storm Sewer Utility Funds.
Recommendation:
Staff recommends adopting Resolution #25-102 awarding construction staking contract for High Point Street Reconstructions, Improvement Project #25-05.
Outcome/Action:
Motion to adopt Resolution #25-102 awarding construction staking contract for High Point Street Reconstructions, Improvement Project #25-05.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 05/07/2025 01:56 PM |
| Brian Hagen | Brian Hagen | 05/08/2025 02:37 PM |
- Form Started By:
- Joe Feriancek
- Started On:
- 05/05/2025 10:17 AM
- Final Approval Date:
- 05/08/2025