City Improvement Projects
2026 Pavement Management Program Projects
City of Anoka Improvement Projects
Ferry Street (Trunk Highway 47) Grade Separation of BNSF Rail Crossing
Anoka County Improvement Projects
MnDOT Improvement Projects
Studies & Items of Interest
Wetland 114 P staff updates
PWC Future Topics Calendar Discussion Items
See calendar in the next case.
City Improvement Projects
2026 Pavement Management Program Projects
- Obtaining/reviewing topographic surveys, geotechnical evaluations and utility testing
- Preparing plans and specifications
- 2026 construction
- Construction complete
- Project close out Summer 2025
- Construction in progress
- Substantial completion anticipated by May 30th
- Bid opening May 21st
- 2025 construction
- Executing contracts / scheduling preconstruction meeting
- Construction anticipated to begin late June/early July
- Construction will commence soon
- Construction scheduled to begin May 19th
- Bid opening May 21st
- 2025 construction
- See separate case
- Construction almost complete
- 2025 construction
- 2025 construction
- Obtaining estimate from Connexus to light Ramsey Parkway and intersections
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Substantially complete
- Punch list items are being addressed
- Construction in progress
- Substantial completion Summer 2025
- 2025 construction
- Change Order 34 to IP #20-11, Ramsey Gateway Highway 10 Improvements
- Bolton & Menk prepared plans and specs for 10’ trail construction
- Meeting with MnDOT soon to discuss cost contribution and project schedule
- Construction complete
- Punch list items are being addressed
- Construction complete
- Waiting for seed to germinate before issuing final payment
- Construction in progress
- Substantial completion October 15, 2025
- Final completion December 31, 2025
- Sunfish Lake Blvd grade separations (RR and TH10) substantially complete
- Ramsey Blvd grade separations (RR and TH10) construction in progress
- Final completion anticipated June 2026
- Project webpage https://www.anokacountymn.gov/3918/Hwy-10Ramsey-Blvd-Interchange
City of Anoka Improvement Projects
Ferry Street (Trunk Highway 47) Grade Separation of BNSF Rail Crossing
- City-led project
- $45M in bonds authorized October 2020
- 2028 construction anticipated
- Combined with above City-led project
- 3-lane design
- Received regional solicitation funds for 2027 construction
- Permanent signal system at McKinley Street
- Construction proposed for 2027 - 2029
Anoka County Improvement Projects
- No updates.
MnDOT Improvement Projects
- No updates.
Studies & Items of Interest
Wetland 114 P staff updates
- Staff continues to monitor water levels. Will provide updates as applicable.
- Staff can respond to questions as needed.
PWC Future Topics Calendar Discussion Items
See calendar in the next case.
Notification:
Notification is not required.
Time Frame/Observations/Alternatives:
Staff estimates up to 10 minutes will be needed for updates and discussion.
Recommendation:
Staff can offer recommendations on specific items upon request.
Outcome/Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Marsha Weidner | 05/15/2025 02:56 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 05/15/2025 12:06 PM
- Final Approval Date:
- 05/15/2025