6.1.
| Public Works Committee |
| Meeting Date: | 07/15/2025 |
| Primary Strategic Plan Initiative: | {ud_pd8} |
Title:
Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
#26-01 MSA Bunker Lake Boulevard Reconstruction
City of Anoka Improvement Projects
Ferry Street (Trunk Highway 47) Grade Separation of BNSF Rail Crossing
Anoka County Improvement Projects
MnDOT Improvement Projects
Highway 10 Mill & Overlay and RCI Improvements
Studies & Items of Interest
Wetland 114 P staff updates
PWC Future Topics Calendar Discussion Items
See calendar in the next case.
City Improvement Projects
#26-01 MSA Bunker Lake Boulevard Reconstruction
- Bolton & Menk, Inc. preparing final plans and specifications
- 2026 construction proposed
- Preparing plans and specifications
- 2026 construction proposed
- Preparing plans and specifications
- 2026 construction proposed
- Preparing plans and specifications
- 2026 construction proposed
- Preparing plans and specifications
- 2026 construction proposed
- Preparing plans and specifications
- 2026 construction proposed
- Preparing plans and specifications
- 2026 construction proposed
- Preparing plans and specifications
- 2026 construction proposed
- Construction complete
- Project close out Summer 2025
- Construction in progress
- Fall completion anticipated
- Construction starting July 14 - Dave Perkins Contracting
- Temp water connections required during construction of new watermain
- Substantial completion anticipated Fall 2025
- Construction in progress
- Construction complete
- Punch list items are being addressed
- Rum River Hills complete
- Village of Sunfish Lake construction in progress
- Late Summer completion anticipated
- Preparing plans and specifications
- Pavement repairs east of Sapphire Street completed separately July 14 - 21
- Construction complete
- Final payment soon
- Preconstruction meeting with Corrective Asphalt Materials, LLC was held July 8th
- Construction starting soon
- Construction started July 9th
- Obtaining estimate from Connexus to light Ramsey Parkway and intersections only
- Staff will present the proposed lighting plan during the meeting
- Construction complete
- Working on as-builts
- Construction complete
- Working on as-builts
- Substantially complete
- Punch list items are being addressed
- Contractor proposes mill and overlay to address poor rideability
- Construction complete
- Punch list items are being addressed
- Construction complete
- Punch list items are being addressed
- Construction substantially complete
- Punch list items are being addressed
- Construction in progress
- Bolton & Menk prepared plans and specs for 10’ trail construction
- Work continues with MnDOT to determine cost contributions and project schedule
- Construction complete
- Punch list items are being addressed
- Construction complete
- Working to ensure adequate seeding germination before issuing final payment
- Construction in progress
- City Council tour anticipated early August
- Working through Change Order #3 and Engineering Amendment #3 requests
- Completion Fall/Winter 2025
- Sunfish Lake Blvd grade separations (RR and TH10) substantially complete
- Bridges will be painted soon, including City logo
- Trail paving will be completed soon
- Additional signing will be installed soon
- Ramsey Blvd grade separations (RR and TH10) construction in progress
- Substantial completion anticipated by end of September
- Final completion anticipated June 2026
- Project webpage https://www.anokacountymn.gov/3918/Hwy-10Ramsey-Blvd-Interchange
City of Anoka Improvement Projects
Ferry Street (Trunk Highway 47) Grade Separation of BNSF Rail Crossing
- City-led project
- $45M in bonds authorized October 2020
- 2028 construction anticipated
- Combined with above City-led project
- 3-lane design
- Received regional solicitation funds for 2027 construction
- Permanent signal system at McKinley Street
- Construction proposed for 2027 - 2029
Anoka County Improvement Projects
- No updates.
MnDOT Improvement Projects
Highway 10 Mill & Overlay and RCI Improvements
- Mill & Overlay US 10/169 pavement from approx. ½-mile west of Cleveland/Jarvis Avenue in Elk River to ½-mile west of Ramsey Boulevard in Ramsey, including Dayton Rest Area
- Construct Reduced Conflict Intersection (RCI) improvements for the intersections of Edison Street and Jarvis Street in Elk River, and Alpine Drive and Beatty Drive in Ramsey
- Construct J-Turns
- Remove median crossings
- Extend pedestrian trail south of US 10/169 from 500-feet East of Adams Street to Edison Street
- Construct pedestrian refuge in median of US 10/169 at Jarvis Street
- Repair/replace culverts
- Construct/repair/replace misc. guardrail treatments
- 2027 construction proposed
Studies & Items of Interest
Wetland 114 P staff updates
- Staff continues to monitor water levels.
- Will provide updates as applicable.
- Staff can respond to questions as needed.
PWC Future Topics Calendar Discussion Items
See calendar in the next case.
Notification:
Notification is not required for this case.
Time Frame/Observations/Alternatives:
Staff estimates up to 60 minutes will be needed for updates and discussion.
Recommendation:
Staff can offer recommendations on specific items upon request.
Outcome/Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 07/11/2025 01:20 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 07/11/2025 11:52 AM
- Final Approval Date:
- 07/11/2025