5.1.
| Public Works Committee |
| Meeting Date: | 09/16/2025 |
| Primary Strategic Plan Initiative: | {ud_pd8} |
Title:
Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
#26-01 MSA Bunker Lake Boulevard Reconstruction
City of Anoka Improvement Projects
Ferry Street (Trunk Highway 47) Grade Separation of BNSF Rail Crossing
Anoka County Improvement Projects
MnDOT Improvement Projects
Highway 10 Mill & Overlay and RCI Improvements
Studies & Items of Interest
Wetland 114P Outlet Control Structure
Miscellaneous Staff Updates
PWC Future Topics Calendar Discussion Items
See calendar in following case.
City Improvement Projects
#26-01 MSA Bunker Lake Boulevard Reconstruction
- Bolton & Menk, Inc. preparing final plans and specifications
- 2026 construction proposed
- Preparing plans and specifications in-house
- 2026 construction proposed
- Preparing plans and specifications in-house
- 2026 construction proposed
- Preparing plans and specifications in-house
- 2026 construction proposed
- Preparing plans and specifications in-house
- 2026 construction proposed
- Preparing plans and specifications in-house
- 2026 construction proposed
- Preparing plans and specifications in-house
- 2026 construction proposed
- Preparing plans and specifications in-house
- 2026 construction proposed
- Construction complete
- Punch list items are being addressed
- Construction in progress
- Fall completion anticipated
- Construction in progress
- Fall completion anticipated
- Construction substantially complete
- Construction substantially complete
- Construction substantially complete
- Preparing plans and specifications in-house
- 2026 construction
- Construction almost complete…PW parking lot to be completed September 12th
- Connexus hopes to submit an estimate before the September PWC meeting
- Street lights along Ramsey Parkway and at intersections
- Damon Farber preparing plans and specifications
- Utilized geotechnical soil borings from COR Mass Grading for structural design work
- On schedule for July 1, 2026, grand opening
- Will present case at October PWC meeting to discuss use of CMAR/CMAA
- Staff will present additional updates during the meeting
- Construction complete
- Closing project out this Fall
- Construction complete
- Contractor milled and overlayed Xkimo Street to address poor rideability
- Construction complete
- Closing project out this Fall
- Construction complete
- Closing project out this Fall
- Construction complete
- Waiting for latest round of seed to germinate
- Bolton & Menk prepared plans and specs for 10’ trail construction
- Work continues with MnDOT to determine cost contributions and project schedule
- Construction complete
- Working to ensure adequate seed germination before issuing final payment
- Construction complete
- Working to ensure adequate seed germination before issuing final payment
- Construction in progress
- City Council tour in December
- Final Completion December 31, 2025
- Mailing general information letters (FAQ’s) with 3rd quarter utility bills
- Sunfish Lake Blvd grade separations (RR and TH10) substantially complete
- Ramsey Blvd grade separations (RR and TH10) substantially complete September 16th
- Final completion anticipated June 2026
- Project webpage https://www.anokacountymn.gov/3918/Hwy-10Ramsey-Blvd-Interchange
City of Anoka Improvement Projects
Ferry Street (Trunk Highway 47) Grade Separation of BNSF Rail Crossing
- City-led project
- $45M in bonds authorized October 2020
- 2028 construction anticipated
- Combining with above City-led project
- 3-lane design
- Received regional solicitation funds for 2027 construction
- Permanent signal system at McKinley Street
- Construction proposed for 2027 - 2029
Anoka County Improvement Projects
- No updates.
MnDOT Improvement Projects
Highway 10 Mill & Overlay and RCI Improvements
- Mill & Overlay US 10/169 pavement from approx. ½-mile west of Cleveland/Jarvis Avenue in Elk River to ½-mile west of Ramsey Boulevard in Ramsey, including Dayton Rest Area
- Construct Reduced Conflict Intersection (RCI) improvements for the intersections of Edison Street and Jarvis Street in Elk River, and Alpine Drive and Beatty Drive in Ramsey
- Construct J-Turns
- Remove median crossings
- Extend pedestrian trail south of US 10/169 from 500-feet East of Adams Street to Edison Street
- Construct pedestrian refuge in median of US 10/169 at Jarvis Street
- Repair/replace culverts
- Construct/repair/replace misc. guardrail treatments
- 2027 construction proposed
Studies & Items of Interest
Wetland 114P Outlet Control Structure
- Staff continue to monitor water levels and will provide updates as applicable.
- Staff can respond to questions as needed.
Miscellaneous Staff Updates
- No Parking signs will be installed on one side of streets in Village of Sunfish Lake development
- Resolution #03-04-095 & April 18, 2003, City staff review letter required no-parking on one side of all streets since streets were constructed 28-feet wide BOC - BOC
- No Parking signs do not exist
- Traffic Control Request Policy
- Preparing draft policy
PWC Future Topics Calendar Discussion Items
See calendar in following case.
Notification:
Notification is not required for this case.
Time Frame/Observations/Alternatives:
Staff estimates up to 30 minutes will be needed for updates and discussion.
Recommendation:
Staff can offer recommendations on specific items upon request.
Outcome/Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Marsha Weidner | 09/11/2025 02:40 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 09/11/2025 08:56 AM
- Final Approval Date:
- 09/11/2025