4.11.
CC Regular Session
- Meeting Date:
- 05/22/2012
- Submitted For:
- MaryJo Warner
- By:
- MaryJo Warner, Engineering/Public Works
Information
Title:
Adopt Resolution #12-05-XXX Authorizing Partial Payment to Knutson Construction for IP10-22 Municipal Parking Ramp, Phase II
Background:
Resolution and Pay Request Attached.
Recommendation:
Public Works Director/Principal City Engineer, Brian Olson has inspected the completed work and recommends partial payment to Knutson Construction in the amount of $75,050.00.
Council Action:
Motion to adopt Resolution 12-05-XXX authorizing partial payment to Knutson Construction for IP 10-22 Ramsey Municipal Parking Facility Phase II in the amount of $75,050.00.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Kurt Ulrich | Kurt Ulrich | 05/17/2012 02:57 PM |
- Form Started By:
- MaryJo Warner
- Started On:
- 05/15/2012 02:06 PM
- Final Approval Date:
- 05/17/2012