4.12.
CC Regular Session
- Meeting Date:
- 10/22/2013
- Submitted For:
- Bruce Westby
- By:
- MaryJo Warner, Engineering/Public Works
Information
Title
Adopt Resolution #13-10-180 Approving Partial Payment to Douglas-Kerr Underground LLC for IP 13-11 COR TWO Site Improvements
Purpose/Background:
To review and approve the attached Resolution and Pay Request.
Recommendation:
The Engineering Technician IV has inspected the completed work and recommends partial payment to Douglas-Kerr Underground, LLC for IP 13-11 COR TWO Site Improvements in the amount of $67,516.59.
Action:
Motion to adopt Resolution #13-10-180 approving partial payment to Douglas-Kerr Underground, LLC for IP 13-11 COR TWO Site Improvements in the amount of $67,516.59.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 10/16/2013 11:23 AM |
| Kurt Ulrich | Kurt Ulrich | 10/17/2013 02:47 PM |
- Form Started By:
- MaryJo Warner
- Started On:
- 10/14/2013 01:47 PM
- Final Approval Date:
- 10/17/2013