4.5.
CC Regular Session
Meeting Date:
01/28/2014
By:
Bruce Westby, Engineering/Public Works

Information

Title

Adopt Resolution #14-01-022 Authorizing Final Payment to North Valley, Inc. for IP 12-23, Alpine Drive Reconstruction.

Purpose/Background:

To review and approve the attached Resolution and Pay Request.

Notification:

No notifications were required for this item.

Observations/Alternatives:

The final project cost was greater than the contract cost due to increased grading quantities related to the pathway construction south of Alpine Drive.

Recommendation:

The Engineering Technician IV has inspected the completed work and recommends final payment be made to North Valley, Inc. for IP 12-23, Alpine Drive Reconstruction, in the amount of $5,929.77.

Action:

Motion to adopt Resolution #14-01-022 authorizing final payment to North Valley, Inc. for IP 12-23, Alpine Drive Reconstruction, in the amount of $5,929.77.

Attachments

Form Review

Inbox Reviewed By Date
Len Linton Len Linton 01/23/2014 10:42 AM
Kurt Ulrich Kurt Ulrich 01/23/2014 12:49 PM
Form Started By:
Bruce Westby
Started On:
01/17/2014 08:37 AM
Final Approval Date:
01/23/2014