Continue discussion of Shared Fire Services
Purpose/Background:
Background:
October of 2011 the cities of Ramsey, Nowthen and St Francis met to discuss the feasibility of some form of Shared Fire Service. At the first meeting it was decided to open the discussions to Oak Grove and Bethel to look at regional effort.
Resolutions were passed in October 2011 by each of the cities verbalizing the goals and purpose of the effort:
Study group was made up from the following of each community:
On April 12, 2012 the Study Group made a presentation at Ramsey to all 5 communities. The PowerPoint presentation summarized the Final Report that the Study Group had generated. (Attached are both PowerPoint and Final Report) Issues identified within the Final Report were:
On May 22, 2012 Ramsey council discussed case #7.04 and passed resolution #12-05-075 to continue efforts towards a shared fire service. (Resolution attached)
Later in 2012 the 5 communities applied and were successful at receiving a grant to hire a consultant to further research a consolidation. The consultants (ESCI) Feasibility Study was received and a presentation was made on June 26, 2013 at Ramsey to the 5 communities (Study Attached) The conclusion of the study is lengthy but the opening statement contains the following statement: “Several of the study departments currently share certain services and work homogenously while all of the study departments benefit from mutual aid response from one another. Expanding the existing spirit of cooperation to gain even more efficiencies is the next logical step.”
On August 13, 2013, the Ramsey council discussed case #7.01 and passed resolution #13-08-133 to continue efforts towards a shared fire service.
Since then the Study Group has continued to meet. It has identified the following issues that have also been noted in the Study Groups Final Report and are noted in the ESCI Feasibility Study. It was the Study Groups decision to focus on the following:
The Administrator's group met outside the Study group and generated a proposed draft Cost Share Model for discussion. Within the Study Group, the consensus was that outside expertise was needed to generate a draft JPA and create a plan to bring the Relief Associations up to the highest group’s level. Quotes were received for both endeavors.
In May 2014 the cities of Nowthen, St Francis and Bethel all passed resolutions to hire two consultants to address the JPA and Relief issues. Ramsey Council, after discussion tabled the case.
At the May 21, 2014 Study Group meeting, it was the consensus of the group to only pursue work on the JPA at this time, and address the Relief Association issues afterward when, and if, a consensus is developed on the governance structure of a new organization.
October of 2011 the cities of Ramsey, Nowthen and St Francis met to discuss the feasibility of some form of Shared Fire Service. At the first meeting it was decided to open the discussions to Oak Grove and Bethel to look at regional effort.
Resolutions were passed in October 2011 by each of the cities verbalizing the goals and purpose of the effort:
- Provide basic city services in an efficient manner
- Work cooperatively across community borders
- Establish a Joint Fire Study Group to look at the feasibility of a Shared Fire Service Group.
- The study group would report back to all communities by April 1, 2012 with a recommendation to the feasibility of the study
Study group was made up from the following of each community:
- Administrator
- Elected Official
- Fire Chief
- Member of respective fire dept.
On April 12, 2012 the Study Group made a presentation at Ramsey to all 5 communities. The PowerPoint presentation summarized the Final Report that the Study Group had generated. (Attached are both PowerPoint and Final Report) Issues identified within the Final Report were:
- Issues of Relief Associations
- Allocation of existing capital and debt
- Possible increase in budgets for some
- Identity issues
- Governance-People and Structure
- Benefits to Firefighters
- Perception of “Loss of Control”
- Differing Levels of Service
On May 22, 2012 Ramsey council discussed case #7.04 and passed resolution #12-05-075 to continue efforts towards a shared fire service. (Resolution attached)
Later in 2012 the 5 communities applied and were successful at receiving a grant to hire a consultant to further research a consolidation. The consultants (ESCI) Feasibility Study was received and a presentation was made on June 26, 2013 at Ramsey to the 5 communities (Study Attached) The conclusion of the study is lengthy but the opening statement contains the following statement: “Several of the study departments currently share certain services and work homogenously while all of the study departments benefit from mutual aid response from one another. Expanding the existing spirit of cooperation to gain even more efficiencies is the next logical step.”
On August 13, 2013, the Ramsey council discussed case #7.01 and passed resolution #13-08-133 to continue efforts towards a shared fire service.
Since then the Study Group has continued to meet. It has identified the following issues that have also been noted in the Study Groups Final Report and are noted in the ESCI Feasibility Study. It was the Study Groups decision to focus on the following:
- Develop a proposed draft Cost Share Model that is equitable for each community (See attached - note this is subject to revisions (per the footnotes on the document) that address the need to apportion administrative expenses)
- Work towards a draft JPA that would address Governance details
- Look at a plan that would bring all three Relief benefits up to the level of the highest group.
The Administrator's group met outside the Study group and generated a proposed draft Cost Share Model for discussion. Within the Study Group, the consensus was that outside expertise was needed to generate a draft JPA and create a plan to bring the Relief Associations up to the highest group’s level. Quotes were received for both endeavors.
In May 2014 the cities of Nowthen, St Francis and Bethel all passed resolutions to hire two consultants to address the JPA and Relief issues. Ramsey Council, after discussion tabled the case.
At the May 21, 2014 Study Group meeting, it was the consensus of the group to only pursue work on the JPA at this time, and address the Relief Association issues afterward when, and if, a consensus is developed on the governance structure of a new organization.
Timeframe:
Funding Source:
This is for discussion only. Depending on Council direction, a case will be brought to a regular council meeting for action.
Responsible Party(ies):
Outcome:
Staff is looking for direction on how this process is to proceed. The issues mentioned above including governance, cost sharing will be addressed in a draft JPA document. Other detailed questions such as City "weighted" decision-making has been brought up, and the study group agrees this must be addressed in an equitable manner via the draft JPA document.
Attachments
- Press Release
- Study Group Final Report
- Resolution May 12-05-075
- Resolution 13-08-133
- Cost Share Model
Form Review