4.7.
CC Regular Session
- Meeting Date:
- 07/28/2015
- Submitted For:
- Patrick Brama
- By:
- Kathy Schmitz, Administrative Services
Information
Title
Adopt Resolution #15-07-180 Approving Partial Payment to Construction Results Corporation for IP #14-28 Parking Ramp Garage Enclosure
Purpose/Background:
Resolution and Pay Request attached.
Recommendation:
SRF Consulting, the project manager hired by the City, has inspected the completed work and recommends partial payment to Construction Results Corporation for IP #14-28, parking ramp enclosure, in the amount of $70,300.00.
Action:
Motion to Adopt Resolution #15-07-180 Approving Partial Payment to Construction Results Corporation for IP #14-28 Parking Ramp Garage Enclosure.