5.2.
Public Works Committee
Meeting Date:
03/15/2016
By:
Bruce Westby, Engineering/Public Works

Title:

Staff Updates on Improvement Projects/Items of Interest

Purpose/Background:

The purpose of this case is to update the Committee on various active and proposed improvement projects within the City, and on other items of interest to the Committee.  Below are lists of the various improvement projects and items of interest that the Committee will be updated on.

Improvement Projects
 
  • US 10 & CR 83/Armstrong Boulevard Interchange
    • Signal work continues
    • All remaining work resumes next week
    • Speed limit restriction signs will be reinstalled until project completion
    • Project completion in late May
  • Business Park 95 Regional Stormwater Pond Improvements
    • Surveying site
    • Reviewing options for cost savings
    • Plans should be complete in April
    • Summer / fall construction (dry season)
  • Andrie Street & 164th Lane Reconstruction
    • Plans and specs are nearly complete
    • State Aid to review plans and specs mid-March / early April
    • Project update letters will soon be mailed to residents
    • March 16th - Private utilities coordination meeting
    • March 22nd - Council to consider approving No Parking Resolution
    • April 12th - Council to consider approving plans and specs & authorize ads for bids
    • May 24th - Council to consider accepting bids & awarding construction contract
    • Construction begins early June 2016
    • Project complete October 2016
  • 2016 Overlay Project
    • Sunwood Drive - Sunfish Lake Blvd. to bridge between 147th Ln & Krypton St (+/- 0.8 mile)
    • March 22nd - Council to consider accepting Feasibility Report & ordering Public Hearing for April 12th
    • April 12th - Council to conduct Public Hearing & authorize plans and specs
    • June 14th - Council to consider approving plans and specs & authorize ads for bids
    • July 26th - Council to consider accepting bids & awarding construction contract
    • Construction begins early August
    • Project complete mid-September
  • 2016 Sealcoat Project
    • May 10th - Council to consider approving plans and specs & authorize ads for bids
    • June 14th  - Council to consider accepting bids & awarding construction contract
    • Construction begins early July 2016
    • Project complete August 2016
  • Riverdale Drive Extension - Traprock St. to Ramsey Blvd. 
    • Plans and specs in progress
    • Working with Anoka Parks for mutually beneficial acquisition of 5.3 acres roadway right-of-way
  • TH 47 Crosswalk Improvements @ Nowthen Blvd / Xkimo Street
    • Master Partnership Contract #1001234 executed
    • TH 47 trail LUP required by MnDOT...in progress
    • Staff completed concrete, striping and traffic control plans
    • MnDOT working on signal system revision plans
    • Work to occur this spring, unless significant savings are available if pairing w/ MnDOT project
  • Sunwood Drive Concrete Pavement Improvements
    • Concrete pavement needs repairs in numerous areas, especially in crosswalks
    • Work not budgeted in 2016
    • Weighing options for temporary crosswalk repairs in 2016
    • Project proposed for 2017
  • Sunwood Drive Striping Improvements
    • Coordinate with concrete pavement improvements

Items of Interest 
 
  • Gibbon Street & 173rd Avenue Drainage Improvements Feasibility Report
  • Woodland Green Park drainage issues - Dead trees have been removed
  • Trail Maintenance Policy
  • Stormwater Pond Maintenance Policy

Timeframe:

Staff estimates 15 minutes will be needed for updates and discussion.

Observations/Alternatives:

N/A

Funding Source:

N/A

Recommendation:

N/A

Action:

Dependent on Committee discussion and direction.

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Grant Riemer Grant Riemer 03/10/2016 10:56 AM
Kurt Ulrich Kurt Ulrich 03/10/2016 12:29 PM
Form Started By:
Bruce Westby
Started On:
03/08/2016 05:54 PM
Final Approval Date:
03/10/2016