6.1.
Public Works Committee
Meeting Date:
05/17/2016
By:
Bruce Westby, Engineering/Public Works

Title:

Staff Updates on Improvement Projects and Items of Interest

Purpose/Background:

The purpose of this case is to update the Public Works Committee on active and proposed improvement projects within the City, and on other items of interest to the Committee as noted below.

MnDOT Improvement Projects
 
  • TH 47 at 142nd Avenue
    • Remove left turns from southbound TH 47 to eastbound 142nd Avenue
    • Construction proposed to occur this fall
Anoka County Improvement Projects
 
  • US 10 & CR 83/Armstrong Boulevard Interchange
    • Traffic signals fully operational May 23rd (after all lanes are opened to traffic)
    • Llama Street access to Highway 10 is closed
    • Westbound median crossover at Traprock Street is closed
    • May 20th - Ribbon cutting ceremony @ 11 AM
    • Late May - Project completion
  • CR 83/Armstrong Boulevard Pavement Reclamation and Overlay – 150th Lane to 173rd Avenue
    • Pavement to be reclaimed and overlaid with 4” new pavement
    • Bypass lanes added at 154th, 157th, and 163rd Avenues
    • Right turn lanes added at 155th and Tiger Avenues
    • Work will not interfere with Game Fair event
    • Project schedule TBD
  • CR 116/Bunker Lake Boulevard Pavement Reclamation and Overlay – Ramsey Boulevard to Basalt Street
    • Pavement to be reclaimed and overlaid with 4” new pavement
    • Considering striping for left turns to Azurite Street from westbound CR 116
    • Project schedule TBD
City Improvement Projects
 
  • Business Park 95 Regional Stormwater Pond Improvements
    • May 24th - Council considers approving plans & authorizing bids
    • Rerouting storm sewer through green areas to save costs
    • Summer/fall construction (dry season)
  • Andrie Street & 164th Lane Reconstruction
    • May 17th  - Bids opened
    • May 24th - Council considers accepting bids & awarding contract
    • Construction proposed to begin early June 2016
    • Project completion proposed by early October 2016
  • 2016 Overlay Project
    • Sunwood Drive - Sunfish Lake Blvd. to bridge 0.25 mile west of CSAH 5
    • June 14th - Council considers approving plans & authorizing bids
    • July 26th - Council considers accepting bids & awarding contract
    • Construction proposed to begin early August
    • Project completion proposed by September 16th
  • 2016 Sealcoat Project
    • May 24th - Council considers approving plans & authorizing bids
    • June 28th - Council considers accepting bids & awarding contract
    • Construction proposed to begin early July 2016
    • Project completion proposed by mid-August 2016
  • Riverdale Drive Extension - Traprock St. to Ramsey Blvd.
    • Plans and specifications in progress
    • Parks property appraisal complete
    • Working with Anoka Parks for mutually beneficial acquisition of 5.3 acres roadway right-of-way
  • TH 47 Crosswalk Improvements @ Nowthen Blvd / Xkimo Street
    • Master Partnership Contract #1001234 executed 2015
    • May 10th - Council approved TH 47 trail LUP
    • May 24th - Council considers approving Work Order for improvements
    • Staff will complete concrete work and contract striping & traffic control work out
    • MnDOT will contract signal system revisions work out; City to reimburse
    • Construction is proposed to occur late May/early June
  • Sunwood Drive Concrete Pavement Improvements
    • Concrete pavement needs repairs in numerous areas, especially crosswalks
    • Work not budgeted for 2016
    • Temporary pavement repairs to occur in 2016 (est. $15,000)
    • Permanent repairs proposed for 2017 (added to CIP)
  • Sunwood Drive Striping Improvements
    • Coordinate with concrete pavement improvements
Items of Interest
 
  • Woodland Green Park drainage issues - Dead trees removed, hole in pond was requested
  • Others?

Timeframe:

Staff estimates 10 minutes will be needed for updates and discussion.

Observations/Alternatives:

N/A

Funding Source:

N/A

Recommendation:

N/A

Action:

No action required.

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Grant Riemer Grant Riemer 05/12/2016 06:08 AM
Kurt Ulrich Kurt Ulrich 05/12/2016 04:03 PM
Form Started By:
Bruce Westby
Started On:
05/09/2016 04:27 PM
Final Approval Date:
05/12/2016