4.5.
CC Regular Session
- Meeting Date:
- 07/26/2016
- Submitted For:
- Mark Riverblood
- By:
- Mark Riverblood, Engineering/Public Works
Information
Title:
Authorize the Reconditioning of Tennis Courts at Rivers’ Bend Park
Purpose/Background:
The purpose of this case is to approve the reconditioning of 4 (four) tennis courts at Rivers’ Bend Park; and also note that the entrance monument at the park will need to be replaced in the near future.
Both improvements were initially installed with the park's creation in the later part of the 1980's. The tennis courts have been refurbished several times over the years, and the cedar wood-beam monument has also been repainted and 'patched-up' with concrete a few years ago.
Both improvements were initially installed with the park's creation in the later part of the 1980's. The tennis courts have been refurbished several times over the years, and the cedar wood-beam monument has also been repainted and 'patched-up' with concrete a few years ago.
Notification:
No notifications are required, but several of the twice-weekly tennis court users had been apprised that this case was scheduled to be heard at the regular July, 2016 Park and Recreation Commission meeting for a recommendation to City Council. One non-resident was at the meeting advocating for the repairs, and several people submitted e-mails requesting the same.
Observations/Alternatives:
Tennis Courts
Park and Recreation intern, Nathan Greenwald collected information on costs and options on the tennis courts, and presented his findings to the Commission. It was determined that the best option was for a complete reconditioning of the tennis courts with the Armor™ crack repair system, utilizing the contractor with the lowest quote. (Surface Pro of Anoka, Minnesota.) It is believed that the tennis courts could be reconditioned before the end of August, (they would be unavailable for a few work days while under construction).
Park Monument/Sign
As for the monument replacement, staff will be organizing options and costs. At the same time, staff is investigating city-wide way-finding signage and developing iconic signage methods relative to Ramsey's brand. The monument replacement should be considered within this process, anticipated to occur over the next months.
Park and Recreation intern, Nathan Greenwald collected information on costs and options on the tennis courts, and presented his findings to the Commission. It was determined that the best option was for a complete reconditioning of the tennis courts with the Armor™ crack repair system, utilizing the contractor with the lowest quote. (Surface Pro of Anoka, Minnesota.) It is believed that the tennis courts could be reconditioned before the end of August, (they would be unavailable for a few work days while under construction).
Park Monument/Sign
As for the monument replacement, staff will be organizing options and costs. At the same time, staff is investigating city-wide way-finding signage and developing iconic signage methods relative to Ramsey's brand. The monument replacement should be considered within this process, anticipated to occur over the next months.
Funding Source:
For the tennis court resurfacing, the recommended funding source is the Capital Maintenance Fund, formally known as ‘Park Maintenance Fund ’ which has a present balance of approximately $366,000.
Recommendation:
Staff recommends proceeding with the reconditioning of the tennis courts as soon as practicable, due to their regular use. The recommended primary contractor would be Surface Pro LLC. at a not-to-exceed cost of $30,000 (complete court repair and color-coating of $19,000, including the crack repair system of $11,000). A contingency amount of $6,800 for net post removal and replacement was also a part of the Park and Recreation Commission's recommendation. Additional quotes will be obtained for this work as well.
Action:
Motion to approve the reconditioning of the tennis courts at Rivers' Bend Park at a not-to-exceed cost of $36,800, to be funded from the Capital Maintenance Fund.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | Grant Riemer | 07/08/2016 10:39 AM |
| Mark Riverblood (Originator) | Mark Riverblood | 07/20/2016 10:13 AM |
| Grant Riemer | Grant Riemer | 07/20/2016 11:09 AM |
| Kurt Ulrich | Jo Thieling | 07/21/2016 10:47 AM |
| Diana Lund | Diana Lund | 07/21/2016 11:00 AM |
- Form Started By:
- Mark Riverblood
- Started On:
- 07/07/2016 02:17 PM
- Final Approval Date:
- 07/21/2016