4.9.
CC Regular Session
Meeting Date:
08/08/2016
By:
Kathy Schmitz, Administrative Services

Information

Title

Adopt Resolution #16-08-140 Approving Change Order #5 and Partial Payment to Brennan Construction of MN, Inc. for IP #14-30 Fire Station #2.
 

Purpose/Background:

Resolution, Change Orders, and Pay Requests are Attached.
 
STAFF NOTES:
Generally, from a budget perspective, this project is in a positive position (please see attached budget).  The City had $210,000 budgeted for change orders.  At this point, roughly 41% of the project contingency budget has been used, and staff doesn't see anything major coming forward before this project closes out (we do expect a change order #6).  Additionally, between wiring, FF&E, and the generator line items, staff expects the project to come in $120,000 below budget (savings).  Staff, BKV Group, and Brennen Construction have worked together on several occasions throughout this project to eliminate potential change orders and save money within available line items (i.e. FF&E, wiring, and the generator).  Staff is anticipating, at this point, a "budget surplus" will be available at the conclusion of this construction project.

Recommendation:

BKV Group, Inc., the project manager hired by the City, has inspected the completed work and recommends partial payments to Brennan Construction in the amounts of $16,901.63 and $36,941.77 for a total of $53,843.40.

Action:

Motion to:
Adopt Resolution #16-08-140 Approving Change Order #5 and Partial Payment to Brennan Construction of MN, Inc. for IP #14-30 Fire Station #2.
 

Attachments

Form Review

Inbox Reviewed By Date
Kurt Ulrich Kurt Ulrich 05/19/2016 05:28 PM
Matt Kohner Matt Kohner 08/04/2016 03:07 PM
Kurt Ulrich Kurt Ulrich 08/04/2016 03:24 PM
Form Started By:
Kathy Schmitz
Started On:
05/13/2016 08:49 AM
Final Approval Date:
08/04/2016