Skip to main content

AgendaQuick™

View Agenda Item

5.3.
Public Works Committee
Meeting Date:
01/17/2017
By:
Bruce Westby, Engineering/Public Works

Title:

Consider Recommendation to City Council to Accept Draft Feasibility Report for Sunwood Drive Reconstruction, Improvement Project #17-00

Purpose/Background:

The purpose of this case is to consider providing a recommendation to the City Council for accepting the DRAFT Feasibility Report for Sunwood Drive Reconstruction, City Improvement Project #17-00. 

Timeframe:

Staff estimates 20 minutes will be required to present this case and respond to questions.

Observations/Alternatives:

Attached is a DRAFT copy of the Feasibility Report.  Please note this is a working document still under development.

While the majority of information in the attached draft report is complete, the preliminary assessments are currently incomplete.  Before publishing preliminary assessments, Staff wishes to discuss preliminary assessments for this project with the Public Works Committee since the City has not yet applied the adopted Special Assessments Policy to projects assessing commercial or industrial properties.  Staff would therefore like to discuss the optional assessment methods with the Committee before finalizing preliminary assessments within the draft Feasibility Report, which is proposed to be presented to the City Council on January 24th.

Once the Feasibility Report is complete, meetings with individual property owners will be conducted to discuss the proposed project, their preliminary assessment, and to gather feedback for future consideration by Council.

Alternatives:
Alternative #1 – Motion recommending City Council acceptance of the recommendations outlined in the draft Feasibility Report for Sunwood Drive Reconstruction, City Improvement Project #17-00, with the following modifications; ___________.

Alternative #2 – Motion denying City Council recommendation at this time.

Funding Source:

Staff proposes to fund the proposed improvements using a combination of special assessments, street reconstruction bond funds, and stormwater utility funds. Staff proposes to assess 9 identified benefiting property owners for 25% of the eligible project costs totaling $151,750.

Recommendation:

Staff recommends alternative #1.

Action:

Motion to recommend approval of Alternative #1.

Attachments

Form Review

Inbox Reviewed By Date
Grant Riemer Grant Riemer 01/12/2017 03:06 PM
Kurt Ulrich Kurt Ulrich 01/12/2017 04:29 PM
Form Started By:
Bruce Westby
Started On:
01/10/2017 09:07 AM
Final Approval Date:
01/12/2017