4.7.
CC Regular Session
- Meeting Date:
- 03/28/2017
- Submitted For:
- Bruce Westby
- By:
- MaryJo Warner, Engineering/Public Works
Information
Title
Adopt Resolution #17-03-075 Authorizing Partial Payment to DRC, Inc. and Approving Change Order #1 for Ramsey Municipal Complex Site Demolition
Purpose/Background:
Resolution and Pay Request is attached along with a copy of Change Order #1 with supporting invoice. Change Order #1 covers costs outside the scope of the contract as required to test internal fireproof doors for asbestos and to remove and dispose of four (4) doors that were found to contain asbestos. This work totaled $1,230 and is included as part of pay request #2.
Recommendation:
The Senior Engineering Technician has inspected the completed work and recommends partial payment to DRC, Inc. for Ramsey Municipal Complex site demolition in the amount of $31,267.64.
Action:
Motion to adopt Resolution #17-03-075 authorizing partial payment to DRC, Inc. for Ramsey Municipal Complex site demolition in the amount of $31,267.64.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 03/22/2017 02:47 PM |
| Mary Jo Warner (Originator) | MaryJo Warner | 03/22/2017 02:55 PM |
| Bruce Westby | Bruce Westby | 03/23/2017 10:40 AM |
| Mary Jo Warner (Originator) | MaryJo Warner | 03/23/2017 11:18 AM |
| Bruce Westby | Bruce Westby | 03/23/2017 01:10 PM |
| Kurt Ulrich | Kurt Ulrich | 03/23/2017 04:49 PM |
- Form Started By:
- MaryJo Warner
- Started On:
- 03/22/2017 01:52 PM
- Final Approval Date:
- 03/23/2017