Staff Updates on Improvement Projects and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed improvement projects within the City, and on other items of interest to the Committee.
City Improvement Projects
Anoka County Improvement Projects
MnDOT Improvement Projects
Items of Interest
Puma St & Bunker Lake Blvd Infrastructure Improvements
City Improvement Projects
- Business Park 95 Regional Stormwater Pond Improvements (#16-36)
- Work is substantially complete
- Final payment in summer 2017 following satisfactory completion of punch list and warranty work
- Andrie Street & 164th Lane Reconstruction (#16-00 Div. C)
- Work is substantially complete
- Final payment in summer 2017 following satisfactory completion of punch list and warranty work
- Mississippi River Trail Phase 3 (#16-54)
- Work is substantially complete
- Final completion in summer 2017 following satisfactory completion of punch list and warranty work
- Zeolite Street Storm Sewer Extension Improvements (#16-95)
- Work is substantially complete
- Final payment in summer 2017 following satisfactory completion of punch list and warranty work
- Riverdale Drive Extension - Traprock St. to Ramsey Blvd. (#16-20)
- Bid opening July 21
- Council considers accepting bids and awarding construction contract July 25
- Construction substantially complete by mid-October 2017
- Final completion 2018
- Alpine Drive Reconstruction (#17-00)
- Construction starts July 25
- Construction substantially complete September 1
- Final completion 2018
- Road closed August 2017, including during Game Fair
- Sunwood Drive Reconstruction (#17-01)
- Construction starts July 31
- Construction substantially complete September 1
- Final completion 2018
- 2017 Crackseal and Sealcoat Improvements (#17-03)
- Construction to occur in late July and August
- Construction substantially complete by September 1
- Final street sweeping in September
- Sunwood Drive Striping Improvements (#17-04)
- Bid opening July 21
- Council considers accepting bids and awarding construction contract July 25
- Work to occur in August
- Final completion by August 25 (before Happy Days)
- Bunker Lake Boulevard Utilities Extensions (#17-09)
- Construction starts in July
- Construction to be complete by August 25
- Ground Penetrating Radar Pavement Evaluations (#17-11)
- Work to be completed by August 11th
- Soil Borings / Geotechnical Reports 2018/19 Reconstructs/Overlays (#17-12)
- Work to be completed by August 11th
Anoka County Improvement Projects
- Hanson Boulevard/CSAH 78 Grade Separation @ BNSF Railway Crossing (2017)
- Reconstruct County State Aid Highway 78 (CSAH 78) / Hanson Boulevard to a 4-lane divided section
- Construct a grade-separated overpass for Burlington Northern Sante Fe (BNSF) railway crossing
- Hanson Boulevard/CSAH 78 Reconstruction (2018)
- Expand CSAH 78 / Hanson Blvd between 139th Ave and CSAH 18 / Crosstown Blvd to 4-lane divided section
- Foley Boulevard/CSAH 11 Grade Separation @ BNSF Railway Crossing
- This project is currently unscheduled and unfunded
MnDOT Improvement Projects
- Trunk Highway 10 Cable Median Barrier Installation (2018)
- Install cable median barrier along Highway 10 between Thurston Avenue and Highway 101
- Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Railway Crossing (2017)
- Preliminary design in progress
Items of Interest
Puma St & Bunker Lake Blvd Infrastructure Improvements
Timeframe:
Staff estimates that 5 minutes will be needed for updates and discussion.
Observations/Alternatives:
N/A
Funding Source:
N/A
Recommendation:
N/A
Action:
For Committee review and discussion purposes only. No formal action is required.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | Grant Riemer | 07/13/2017 02:21 PM |
| Kurt Ulrich | Kurt Ulrich | 07/13/2017 03:38 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 07/13/2017 12:30 PM
- Final Approval Date: