Skip to main content

AgendaQuick™

View Agenda Item

2.1.
CC Work Session
Meeting Date:
06/28/2011
By:
Mark Riverblood, Engineering/Public Works

Title:

Identify City Maintenance Costs for The Draw

Background:

At the City Council work session of June 7th, 2011, consensus was to issue an RFP for mowing and related services for The Draw.  An outcome of the discussion was the agreement to bring back the city's existing cost to maintain the park in advance of receiving quotes for the contracted work - such that there could be agreement as to the true cost of performing the work in-house.

Staff will carefully review each element of the park's present maintenance costs (within the scope of the  RFP) in a detailed accounting at the meeting.

Funding Source:

None required relating to this case.

Council Action:

Consensus on the method and manner of the cost accounting for the in-house maintenance, based on discussion.

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Kurt Ulrich Kurt Ulrich 06/23/2011 11:13 AM
Form Started By:
Mark Riverblood
Started On:
06/13/2011 01:28 PM
Final Approval Date:
06/23/2011