4.8.
CC Regular Session
- Meeting Date:
- 09/11/2018
- By:
- Bruce Westby, Engineering/Public Works
Information
Title
Adopt Resolution #18-186 Ordering Assessment Roll and Calling Assessment Hearing for Improvement Project #17-02, River's Bend Street Reconstructions
Purpose/Background:
Purpose:
The purpose of this case is to adopt Resolution #18-186 ordering preparation of an assessment roll and calling for an Assessment Hearing at 7 p.m. on October 9, 2018 for Improvement Project #17-02, River's Bend Street Reconstructions.
Background:
City Improvement Project 17-02 involved reconstructing the following street segments within the River’s Bend residential neighborhood;
Pre-Existing Conditions
These street segments in the River’s Bend neighborhood were constructed in 1985 with between 2 and 3½-inches of bituminous pavement, 4-inches of class 5 aggregate base, surmountable concrete curb and gutter, and concrete storm sewer. The streets were 30-foot wide from face-of-curb to face-of-curb, and were centered within a 60-foot wide right-of-way. The pavement was cracksealed and sealcoated in 1988 and in 1995. Spot patching was applied on an as-needed basis since.
In the fall of 2016, the pavement sections of the above-referenced street segments had PASER ratings of 3, meaning they were past the point of overlaying and instead required complete reconstruction.
The existing storm sewer system consisted of concrete catch basins and pipes, which drain runoff from the street to adjacent low-lying areas. Based on design calculations completed by City staff, no modifications were required to the existing storm sewer system.
Municipal sanitary sewer and water utilities existed under many of the pavement sections. The existing utilities were inspected and were found to be in good enough condition that no improvements were required before reconstructing the pavement.
Completed Improvements
All streets were reconstructed matching their existing widths and locations.
After all damaged concrete curb and gutter sections were removed and replaced, the existing bituminous pavement sections were reconstructed using the Full Depth Reclamation (FDR) process. This involved grinding the existing bituminous pavement with an inch or more of existing aggregate base (pavement reclamation), then placing and compacting some of the reclaimed material on top of the reshaped and compacted existing aggregate base. Then, 2-inches of bituminous base course and 1½-inches of bituminous wear course was placed and compacted on top of the compacted reclaim material to provide a pavement section with a 7-ton structural capacity and a 30-plus year design life.
Storm sewer castings were reset after replacing adjusting rings and grouting the insides of the catch basins.
Municipal sanitary sewer and water utility castings were adjusted and reset.
Public Input
Staff met with several of the property owners prior to construction to discuss the improvements and their preliminary assessments. Most generally understood the need for the improvements, though some of the property owners questioned the use of special assessments to help pay for the improvements.
Staff met with numerous other property owners during construction to coordinate construction of various improvements adjacent to or otherwise impacting the use of their properties.
The purpose of this case is to adopt Resolution #18-186 ordering preparation of an assessment roll and calling for an Assessment Hearing at 7 p.m. on October 9, 2018 for Improvement Project #17-02, River's Bend Street Reconstructions.
Background:
City Improvement Project 17-02 involved reconstructing the following street segments within the River’s Bend residential neighborhood;
- 147th Lane from the west River’s Bend plat line to Waco Street,
- 148th Avenue from the west River’s Bend plat line to Xkimo Street,
- Xkimo Street between 147th Lane and 149th Avenue/Sunwood Drive, and
- Yakima Street between 148th Avenue and 149th Avenue/Sunwood Drive.
Pre-Existing Conditions
These street segments in the River’s Bend neighborhood were constructed in 1985 with between 2 and 3½-inches of bituminous pavement, 4-inches of class 5 aggregate base, surmountable concrete curb and gutter, and concrete storm sewer. The streets were 30-foot wide from face-of-curb to face-of-curb, and were centered within a 60-foot wide right-of-way. The pavement was cracksealed and sealcoated in 1988 and in 1995. Spot patching was applied on an as-needed basis since.
In the fall of 2016, the pavement sections of the above-referenced street segments had PASER ratings of 3, meaning they were past the point of overlaying and instead required complete reconstruction.
The existing storm sewer system consisted of concrete catch basins and pipes, which drain runoff from the street to adjacent low-lying areas. Based on design calculations completed by City staff, no modifications were required to the existing storm sewer system.
Municipal sanitary sewer and water utilities existed under many of the pavement sections. The existing utilities were inspected and were found to be in good enough condition that no improvements were required before reconstructing the pavement.
Completed Improvements
All streets were reconstructed matching their existing widths and locations.
After all damaged concrete curb and gutter sections were removed and replaced, the existing bituminous pavement sections were reconstructed using the Full Depth Reclamation (FDR) process. This involved grinding the existing bituminous pavement with an inch or more of existing aggregate base (pavement reclamation), then placing and compacting some of the reclaimed material on top of the reshaped and compacted existing aggregate base. Then, 2-inches of bituminous base course and 1½-inches of bituminous wear course was placed and compacted on top of the compacted reclaim material to provide a pavement section with a 7-ton structural capacity and a 30-plus year design life.
Storm sewer castings were reset after replacing adjusting rings and grouting the insides of the catch basins.
Municipal sanitary sewer and water utility castings were adjusted and reset.
Public Input
Staff met with several of the property owners prior to construction to discuss the improvements and their preliminary assessments. Most generally understood the need for the improvements, though some of the property owners questioned the use of special assessments to help pay for the improvements.
Staff met with numerous other property owners during construction to coordinate construction of various improvements adjacent to or otherwise impacting the use of their properties.
Notification:
Following Council approval, an Assessment Hearing Notice will be published in the City’s official newspaper on Friday, September 21st. Assessment Hearing Notices will also be mailed to all benefiting property owners as required per State Statute.
Anoka County requires that assessments be certified to the County Auditor by November 16th for collection on next year’s taxes. This deadline will be met by conducting the Assessment Hearing at the October 9th City Council meeting, which will also allow adequate time for publication and mailing of Hearing notices.
Anoka County requires that assessments be certified to the County Auditor by November 16th for collection on next year’s taxes. This deadline will be met by conducting the Assessment Hearing at the October 9th City Council meeting, which will also allow adequate time for publication and mailing of Hearing notices.
Observations/Alternatives:
Observations:
At the time this report was prepared, construction of this project was complete with only punch list item work remaining and Staff was calculating final construction costs to assist in determining final assessment amounts for use in publishing and mailing notices for the Assessment Hearing.
Alternatives:
Alternative #1 – Motion to adopt Resolution #18-186 ordering preparation of an assessment roll and calling for an Assessment Hearing at 7 p.m. on October 9, 2018 for Improvement Project #17-02, River's Bend Street Reconstructions.
At the time this report was prepared, construction of this project was complete with only punch list item work remaining and Staff was calculating final construction costs to assist in determining final assessment amounts for use in publishing and mailing notices for the Assessment Hearing.
Alternatives:
Alternative #1 – Motion to adopt Resolution #18-186 ordering preparation of an assessment roll and calling for an Assessment Hearing at 7 p.m. on October 9, 2018 for Improvement Project #17-02, River's Bend Street Reconstructions.
Funding Source:
The construction contract amount for this project is $191,474.48. Street reconstruction project costs include actual construction costs plus 23% indirect costs for administrative (6%), engineering (15%), finance (1%), and legal (1%) costs. Upon adding 23% for indirect costs, the contracted project cost would be $235,513.61. The engineer’s estimate in the Feasibility Report was $301,738.31.
Staff is calculating final construction costs and believes these costs will be only slightly higher than the construction contract amount. No significant quantity revisions or change orders occurred during construction. Final project costs will be reviewed at the Assessment Hearing.
These improvements were included in the City’s Capital Improvement Plan for 2018 construction. Funding sources include a combination of Street Reconstruction and Overlay Program (SROP) bond funds, special assessments to benefiting properties, and stormwater utility funds.
Special Assessments
The City’s Special Assessments Policy (attached) calls for special assessments to pay for 25% of eligible street reconstruction improvement costs. Special assessments are calculated using methods resulting in reasonable and equitable distribution of assessments that are uniform upon the same class of properties within the assessable area. The test for determining the validity of a special assessment is whether the improvement for which the assessment was levied has increased the market value of the property against which the assessment was levied in at least the amount of the assessment.
Ramsey’s Special Assessments Policy identifies three optional methods for calculating assessments; Adjusted Front Footage, Area, and Per Lot. The Feasibility Report for this project identified 44 benefiting residential properties that are proposed to be assessed up to 25% of eligible project costs. On all previous residential street reconstruction projects, the Per Lot assessment method was applied so Staff recommends using the Per Lot method for this project.
All project costs are eligible for special assessments since streets were reconstructed to their pre-existing widths and structural capacities. The preliminarily approved assessment amount was $1,714.42 per parcel, with total assessments amounting to $75,434.58.
A Special Benefit Consultation report is being prepared for this project by the property appraisal and valuation firm of Patchin Messner Dodd and Brumm. This report will help provide proof of benefit to benefiting properties based on the completed improvements. The results of this report, along with the final special assessment amounts as determined by final construction costs, will be discussed with the City Council and the Public during the Assessment Hearing on October 9, 2018.
Staff is calculating final construction costs and believes these costs will be only slightly higher than the construction contract amount. No significant quantity revisions or change orders occurred during construction. Final project costs will be reviewed at the Assessment Hearing.
These improvements were included in the City’s Capital Improvement Plan for 2018 construction. Funding sources include a combination of Street Reconstruction and Overlay Program (SROP) bond funds, special assessments to benefiting properties, and stormwater utility funds.
Special Assessments
The City’s Special Assessments Policy (attached) calls for special assessments to pay for 25% of eligible street reconstruction improvement costs. Special assessments are calculated using methods resulting in reasonable and equitable distribution of assessments that are uniform upon the same class of properties within the assessable area. The test for determining the validity of a special assessment is whether the improvement for which the assessment was levied has increased the market value of the property against which the assessment was levied in at least the amount of the assessment.
Ramsey’s Special Assessments Policy identifies three optional methods for calculating assessments; Adjusted Front Footage, Area, and Per Lot. The Feasibility Report for this project identified 44 benefiting residential properties that are proposed to be assessed up to 25% of eligible project costs. On all previous residential street reconstruction projects, the Per Lot assessment method was applied so Staff recommends using the Per Lot method for this project.
All project costs are eligible for special assessments since streets were reconstructed to their pre-existing widths and structural capacities. The preliminarily approved assessment amount was $1,714.42 per parcel, with total assessments amounting to $75,434.58.
A Special Benefit Consultation report is being prepared for this project by the property appraisal and valuation firm of Patchin Messner Dodd and Brumm. This report will help provide proof of benefit to benefiting properties based on the completed improvements. The results of this report, along with the final special assessment amounts as determined by final construction costs, will be discussed with the City Council and the Public during the Assessment Hearing on October 9, 2018.
Recommendation:
Staff recommends Alternative #1.
Action:
Motion to adopt Resolution #18-186 ordering preparation of an assessment roll and calling for an Assessment Hearing at 7 p.m. on October 9, 2018 for Improvement Project #17-02, River's Bend Street Reconstructions.
Attachments
- Resolution 18-186
- Feasibility Report 17-02
- MSS Chapter 429
- City Charter Chapter 8
- Spec Assessments Policy
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Kurt Ulrich | Kurt Ulrich | 09/06/2018 04:11 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 09/04/2018 06:48 AM
- Final Approval Date:
- 09/06/2018