General Development Patterns - 2018
| Type | Amount |
| Detached Single Family Homes | 126 |
| Multifamily Units | 173 (1 Building) |
| Industrial | 60,000 square feet |
| Commercial | 28,000 square feet |
| New Construction Value | $35M |
Affinity at Ramsey (Inland Group)
This 173 unit senior housing development located west of Center Street, north of Sunwood Drive is under construction. The project site was previously land owned by the City. The project encountered some minor delays due to weather conditions in early fall. Completion is planned by the end of 2019.
Brookside Elementary School (Anoka Hennepin School District No. 11)
This 225,000 square foot elementary school located east of Nowthen Boulevard at 170th Avenue plans to house approximately 800 students. Construction is planned to complete in time for the Fall 2019 start to the 2019-2020 Academic Year.
Bunker Lake Industrial Park (PSD, LLC)
This proposed 60,000 square foot industrial building is planned for south of Bunker Lake Boulevard, west of Armstrong Boulevard. This is the third building in the Bunker Lake Industrial Park. Construction is for the week of November 5. The Developer needs to submit final fees and documents.
Connexus Solar Farm
Construction of this 17-acre solar farm and battery storage utility located south of Highway 10, west of Llama Street is nearing completion. Production is expected to begin in late 2018 or early 2019.
Cottages at The COR (Centra Homes)
This 40 unit detached townhome development is located on City-Owned Property at the southwest intersection of Ramsey Boulevard and Bunker Lake Boulevard. The Developer is working on final plan revisions so that the real estate transaction and required agreements can be executed. Centra Homes expects to commence construction this fall.
Greenway Terrace (Aeon)
Construction on this 47 unit multifamily development is complete. The Project Site was previously owned by the City. The project is fully occupied. A second phase is planned for 2019 construction.
Lazydays RV
This is the former Shorewood RV located on the south side of Highway 10 west of Armstrong Boulevard. Lazydays RV is planning a second building focused on a new service center. The Developer is completing required plan revisions. A case approving final plans is expected for November 13. Lazydays RV expects to start construction this Fall.
Regency Ponds Self Storage
This planned self-storage facility planned to be located at the northeast intersection of Ramsey Boulevard and Bunker Lake Boulevard is currently on hold. The original Developer is attempting to sell the project to a new Developer. The new Developer is revising plans based on City direction and comment.
Springs at Ramsey (Continental Properties)
This 300-unit rental townhome development was being explored for the northwest intersection of Bunker Lake Boulevard and Armstrong Boulevard, abutting Ramsey Fire Station No. 1. There was no official submittal or application. Staff has not received any recent updates from the Developer, so it is unknown if there is a plan to move forward.
Funding Source:
Recommendation:
Action:
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Sean Sullivan | Sean Sullivan | 11/02/2018 09:23 AM |
| Brian Hagen | Tim Gladhill | 11/02/2018 10:09 AM |
- Form Started By:
- Tim Gladhill
- Started On:
- 11/02/2018 08:34 AM
- Final Approval Date:
- 11/02/2018