4.9.
CC Regular Session
- Meeting Date:
- 12/11/2018
- Submitted For:
- Bruce Westby
- By:
- Marsha Weidner, Engineering/Public Works
Information
Title
Adopt Resolution #18-260 Authorizing Partial Payment No. 3 to North Valley, Inc. Improvement Project #17-02, Rivers Bend Street Reconstruction.
Purpose/Background:
Resolution and Pay Request Attached.
Recommendation:
The Senior Engineering Technician has inspected the completed work and recommends partial payment no. 3 to North Valley, Inc. for Improvement Project #17-02, Rivers Bend Street Reconstruction in the amount of $6,383.83.
Action:
Motion to adopt Resolution #18-260 authorizing partial payment no. 3 to North Valley, Inc. for Improvement Project #17-02, Rivers Bend Street Reconstruction in the amount of $6,383.83.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 12/05/2018 02:35 PM |
| Kurt Ulrich | Kurt Ulrich | 12/06/2018 11:41 AM |
- Form Started By:
- Marsha Weidner
- Started On:
- 12/04/2018 11:50 AM
- Final Approval Date:
- 12/06/2018