Adopt Resolution #19-230 Authorizing Partial Payment #2 to Northern Lines Contracting, Inc. for Improvement Project #18-09, COR Infiltration Basin Improvements.

Purpose/Background:

Resolution and Pay Estimate #2 attached.

Recommendation:

The Engineering Technician IV has inspected the completed work and recommends approving partial payment #2 to Northern Lines Contracting, Inc. for Improvement Project #18-09, COR Infiltration Basin Improvements, in the amount of $36,293.47.

Action:

Motion to adopt Resolution #19-230 authorizing partial payment #2 to Northern Lines Contracting, Inc. for Improvement Project #18-09, COR Infiltration Basin Improvements, in the amount of $36,293.47.

Attachments

Form Review

Inbox Reviewed By Date
Bruce Westby Bruce Westby 09/18/2019 12:49 PM
Bruce Westby Bruce Westby 09/18/2019 02:25 PM
Kurt Ulrich Kurt Ulrich 09/19/2019 03:34 PM
Form Started By:
Marsha Weidner
Started On:
09/16/2019 10:41 AM
Final Approval Date:
09/19/2019