6.2.
Public Works Committee
- Meeting Date:
- 11/19/2019
- By:
- Bruce Westby, Engineering/Public Works
Title:
Staff Updates on Improvement Projects and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed improvement projects within the City, and on other items of interest to the Committee.
City Improvement Projects
Anoka County Improvement Projects
MnDOT Improvement Projects
Items of Interest
City Improvement Projects
- The COR Regional Infiltration Basin (#18-09)
- Grading and storm sewer work is complete
- Lift station not operable; control panel not yet installed
- Exploring options to remove sand (8K CY) and topsoil (12K CY) stockpiles
- WMO Permit extended to June 30, 2020
- Ford Brook Estates Street Reconstructions (#19-01)
- Final assessments adopted ($3,919.90 + $1,197.00 = $5,116.90)
- 3 of 8 PO’s paid their full assessment (no partials) as of November 14
- Punch list work and final payment in 2020
- Wood Pond Hills and Chestnut Ridge Street Reconstructions (#19-03)
- Final assessments adopted ($1,445.00)
- 13 of 59 PO’s have paid their assessment as of November 14
- Punch list work and final payment in 2020
- RTC 9th Addition Pond Lining Improvements (#19-06)
- Construction is proposed to start the week of November 18
- Final completion will occur in the spring of 2020
- Wetland 114P Outlet Control Improvements (#19-07)
- Engineering Staff will collect topographic survey data this winter
- Construction proposed for 2020
- Germanium Street Drainage Improvements (#19-09)
- Engineering Staff developing plans
- Construction proposed for 2020
- Hedgehog Street Drainage Improvements (#19-10)
- Bids will be opened October 30, 2019
- Construction in late 2019/early 2020
Anoka County Improvement Projects
- Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive
- Anoka County received $1.35M in HSIP funds (est. project cost = $1.5M)
- Anoka County and City of Ramsey share is $150,000 each (per $1.5M est.)
- Anoka County to begin project design in 2020
- Construction is planned for 2022/2023 pending City and County approvals
- CSAH 116 & TH 47 Intersection Improvements
- Constructing additional turn lanes to improve congestion and safety
- Public open house was held at Anoka High School on November 7
- Pedestrian facility connections under discussion
MnDOT Improvement Projects
- Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
- Preliminary design on hold - MnDOT exploring realignment of Highway 47 to remove S-curve at Anoka County fair grounds
- TH 47 traffic study in progress
- MnDOT may combine project with Anoka Solution improvements
Items of Interest
- Northwest Metro Surface Water Supply Feasibility Study
- Study is roughly 60% complete
- Member cities include Corcoran, Dayton, Ramsey and Rogers
- MCES is funding 100% using Clean Water Funds
- Completion anticipated early 2020
- Centralized Water Treatment Facility Study
- Kickoff meeting held on November 7
- Data exchange in progress
- Completion anticipated before June 2020
- Ramsey Gateway Highway 10 Improvements
- Layout of preferred vision is complete
- Additional updates will be provided during the meeting
Timeframe:
Staff estimates up to 10 minutes will be needed for updates and discussion.
Observations/Alternatives:
N/A
Funding Source:
N/A
Recommendation:
N/A
Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | Grant Riemer | 11/14/2019 12:26 PM |
| Kurt Ulrich | Kurt Ulrich | 11/14/2019 04:15 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 11/13/2019 09:29 AM
- Final Approval Date:
- 11/14/2019