Review Draft Feasibility Study for Centralized Water Treatment Facility
Purpose/Background:
The purpose of this case is to receive a presentation from Chris Larson with SEH, Inc. on the draft City of Ramsey Centralized Water Treatment Facility Study. A link was recently sent via email to SEH's FTP (file transfer) site to allow a copy of the draft study to be downloaded for review prior to the work session. Chris' presentation will touch on the broader topics within the study, along with the primary findings, after which approximately 30 minutes will be reserved for a question and answer session.
Timeframe:
The presentation and question and answer session will conclude by 7:15 PM.
Funding Source:
N/A
Responsible Party(ies):
The City Engineer will introduce the case, after which Chris Larson with SEH will make a formal presentation.
Outcome:
A hard copy of the study will be distributed to each City Council member at the meeting.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Kurt Ulrich | Kurt Ulrich | 07/16/2020 04:27 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 06/30/2020 11:28 AM
- Final Approval Date:
- 07/16/2020