Skip to main content

AgendaQuick™

View Agenda Item

7.1.
CC Regular Session
Meeting Date:
09/08/2020
Submitted For:
Grant Riemer
By:
Grant Riemer, Engineering/Public Works

Information

Title:

Adopt Resolution #20-171 Accepting Bids and Awarding Contracts for Bid Package #1 and Alternate # 1 for the New Public Works Facility

Purpose/Background:

Purpose:
The purpose of this case is to adopt Resolution # 20-171 accepting bids and awarding contracts for Bid Package #1 and Alternate # 1 for the New Public Works Facility.

Background:
The City of Ramsey has long planned for a new public works facility and added it to our Capital Improvement Plan (CIP) in 2006. The land was secured in 2008 by the purchase of the former Bury-Carlson site. That purchase was finalized in 2013 and the  BKV Group was hired in 2015 to perform  a space needs study. This study would be used to determine the size of facility needed to serve the Public Works Department's needs for now and into the future. The size of the current facility is 32,000 sq.ft, which consists of 3 separate buildings with offsite equipment storage spread out over 3 additional sites. The new facility would be approximately 93,000 square feet and is designed to house all Public Works functions and equipment. It is anticipated that the existing buildings will be renovated at a future date and re-used as storage facilities for Public Works and the Police Department, with the current building housing the Utilities Division and Sign Shop to be used as future recycling center.

From the mid 1980's until 1995, the Public Works Department operated out of two pole barns on Highway 47 next the the old Town Hall Building. At that time, the Public Works Department had a total staff of 7 people for all three divisions (Parks Division, Streets Division and Utilities Division). Ramsey's population was 12,400 in 1995. In 1995, the Public Works Department moved into its present location and currently houses 19 full time staff with 11-14 seasonal employees during the summer months. 

Ramsey's current population estimate is 27,400. Additionally, Staff works out of a temporary office trailer that is showing significant signs of deterioration. This proposed facility not only improves operational efficiencies, the office space is in urgent need of replacement to ensure a safe and healthy working condition for Public Works Employees and avoid operating in a facility that could have potential issues with our Property Maintenance Code. 

The current Public Works Facility was actually a series of purchases of existing buildings over a series of several years. None of the current buildings on the campus were constructed by the City. The original purchase represented the size needs at the the time but was not designed for Public Works Operations. In 2005, the Public Works Department added a temporary construction trailer to hold our offices and lunch room with the intent that this would be a stop gap measure until a new facility was constructed. After 15 years, the Public Works Department can no longer operate out of this location efficiently or safely. 

Estimated cost for the new facility is $18.85M for the base bid with an alternate bid for $1.26m to add space to bring the facility to eventual full design build out. The new Public Works Facility is being designed to serve the needs of the City of Ramsey for the next 30-50 years with space to adjust for needs beyond that date. Construction on the new facility is estimated to begin in September of 2020 and be substantially completed in September of 2021.

Notification:

Complete digital Bidding Documents were available online for potential bidders with paper documents also available for viewing at RJM Construction, the City's Construction Manager on this project.

Sealed bids were received at the Ramsey City Hall, 7550 Sunwood Drive NW, Ramsey, MN 55303 until 1:00 p.m., Wednesday, August 26, 2020 at which time bids were publicly opened, reviewed, and read aloud.  Bidders were also able to join the bid opening online. Staff is excited to report that there was great interest in the project in that a total of ninety (90) bids and quotes were received for the ten (10) bid and quote categories.

Observations/Alternatives:

The new PW facility consists of two components at this time,
  1. Main Structure
  2. Alternate # 1 for constructing future expansion today

The reason the addition is being considered for construction at this time is, because of the need for large vehicle storage space. The addition is approximately 12,300 square feet in size. As designed, the main structure will be close to capacity in regard to large vehicle storage. 

With the anticipated growth in the next few years, the City will need to add several large vehicles to keep up with the demand for services. The original design included this space to accommodate this growth, but was scaled back for budgetary reasons. Staff feels the current bidding climate is conducive to adding this addition with the original construction of the new facility. If the addition is constructed now, savings will be realized in mobilization charges, material and labor costs. It's also estimated that to add the space in the future, the future project would include higher costs to re-certify the architectural plans, a probable increase in bonding rates, inflationary costs, changes in building code and a 6 month disruption of the Public Works Facility due to construction. 

After the bids were tabulated, the base bid for Bid Pack # 1 came in at $896,499.00 below the original estimate while the bids for Alternate #1 came in at $27,563.00 above the original estimate.
Bid pack # 1 Estimates
Description Previous Estimate BP #1
low bids
Difference
1A-Special Inspections $52,800.00 $36,682.00 ($16,118.00)
1B-Surveying $24,000.00 $22,160.00 ($1,840.00)
3A-Cast in Place Concrete $950,000.00 $1,194,000.00 $244,000.00
3B-Precast Structural & Arch. Concrete $1,949,998.00 $1,379,458.00 ($570,540.00)
4A-Unit Masonry $374,677.00 $213,240.00 ($161,437.00)
Structural Steel/Misc. Metals Materials $760,400.00 $754,161.00 ($6,239.00)
 
Structural Steel/Misc. Metals Erection $249,700.00 $249,000.00 ($700.00)
7A Waterproofing & Weatherproofing $152,980.00 $41,000.00 ($111,980.00)
14A-Vehicle Lifts $355,323.00 $281,054.00 ($74,269.00)
31A-Earthwork $889,453.00 $636,549.00 ($252,904.00)
32A Asphalt Paving $592,000.00 $619,000.00 $27,000.00
32B-Concrete Paving $168,065.00 $124,900.00 ($43,165.00)
33A- Utilities $469,228.00 $503,809.00 $34,581.00
41A-Overhead Crane System $92,500.00 $83,348.00 ($9,152.00)
Covid Screening & Sanitation $25,000.00 $63,924.00 $38,924.00
Builders Risk Insurance $36,327.00 $27,549.00 ($8,778.00)
Total $7,142,451.00 $6,229,834.00 ($896,499.00)
       
  Alternate # 1    
Description Bid Pack # 1
Estimate
Previous
 Estimate
Difference
Total Alternate Cost $1,294,513.00 $1,266,950.00 $27,563.00

Funding Source:

The funding source is a combination of the Facility Fund, Landfill Fund, Municipal Water, Sanitary Sewer, Street Light, Recycling and Bonding (borrowing/debt).

Recommendation:

Staff recommendation is to accept bids and award contracts for Bid Pack #1 and Alternate # 1 as follows:
BID CATEGORY AWARD AMOUNT
3A-Cast-in-Place Concrete
Northland Concrete & Masonry Company
1125 Stagecoach Road
Shakopee, Mn 55329
Base Bid: $1,194,000.00
Alternate Bid # 1 $153,350.00
3B-Precast Structural & Arch. Concrete
Moline Concrete Products
415 Lilac St
Lino Lakes, Mn 55014
Base Bid: $1,379,458.00
Alternate Bid # 1 $149,649.00
4A-Unit Masonry
SteenBerg-Watrud Construction
10967 Clark Road
Inver Grove Heights, Mn 55077
Base Bid: $213,240.00
Alternate Bid # 1 $0.00
5A- Structural Steel and Misc. Metals-Materials
Thornburg Steel, Inc
23604 University Ave Extension Northwest
Bethel, Mn 55005
Base Bid: $754,161.00
Alternate Bid # 1: $64,000.00
 
5B-Structural Steel and Misc. Metals- Erection
Met-Con Companies
15760 Acorn Trail
Faribault, Mn 55021
Base Bid: $249,000.00
Alternate Bid # 1: $34,000.00
14A- Vehicle Lifts
Midwest Lift Works, LLC
614 Broadway St. N
Jordan, Mn 55352
Base Bid: $281,254.00
Alternate Bid # 1: $0.00
31A- Earthwork
Minnesota Utilities & Excavating
13932 Lake drive NE
Forest Lake, Mn 55025
Base Bid: $636,549.00
Alternate Bid # 1: $12,439.00
32A-Asphalt Paving
Northland Paving
21716 Kenrick Ave South, Suite A
Lakeville, Mn 55044
Base Bid: $619,000.00
Alternate Bid # 1: ($22,000.00)
32B-Concrete Paving
Stapf Concrete Construction
201 W Travelers Trail # 210
Burnsville, Mn 55337
Base Bid: $124,900.00
Alternate Bid # 1: $0.00
33A-Utilities
Jacon, LLC
3900 Labore Road
Vadnais Heights, Mn 55110
Base Bid: $503,809.00
Alternate Bid # 1: ($3,500.00)
Quote Category  
1A-Special Inspections
Intertek PSI
2915 Waters Road, Suite 112
Egan, Mn 55121
Base Bid: $36682.00
Alternate Bid: $0.00
1B-Surveying
Hakenson Anderson
3601 Thurston Ave
Anoka, Mn 55303
Base Bid: $22,160.00
Alternate Bid # 1 $0.00
1C-Final Cleaning *Requested quotes in Bid Package #1.
Rejected quotes at this time, to be bid out in Bid Package # 2
7A-Waterproofing and Weatherproofing
Herzog Coatings
2014 W Alcott Ave
Fergus Falls, Mn 56537
Base Bid; $41,000.00
Alternate Bid # 1 $3,000.00
41A-Overhead Crane Systems
Aero Material Handling Inc
103 Pleasant St
Anoka, Mn 55303
Base Bid: $83,348.00
Alternate Bid # 1: $0.00
   
 
Alternatives
  1. Adopt Resolution #20-171 accepting bids and awarding contracts for Bid Package #1 with a base bid amount of $6,138,361 AND including the Alternate Bid #1 in the amount of $441,938 for a total of $6,580,299.
  2. Adopt Resolution #20-171 accepting bids and awarding contracts for Bid Package #1 with a base bid amount of $6,138,361 WITHOUT including the Alternate Bid #1.
  3. Do not adopt Resolution #20-171 (do not move forward with the project at this time).

Action:

Motion to adopt Resolution #20-171 accepting bids and awarding contracts for Bid Package #1 with a base bid amount of $6,138,361 AND including the Alternate Bid #1 in the amount of $441,938 for a total of $6,580,299.

Attachments

Form Review

Inbox Reviewed By Date
Brian Hagen Grant Riemer 09/03/2020 12:39 PM
Grant Riemer (Originator) Grant Riemer 09/03/2020 12:47 PM
Brian Hagen Grant Riemer 09/03/2020 12:49 PM
Grant Riemer (Originator) Grant Riemer 09/03/2020 12:55 PM
Brian Hagen Tim Gladhill 09/03/2020 03:11 PM
Kurt Ulrich Kurt Ulrich 09/03/2020 04:05 PM
Form Started By:
Grant Riemer
Started On:
08/11/2020 09:47 AM
Final Approval Date:
09/03/2020