Adopt Resolution #20-276 Authorizing Partial Payment #1 to Steenberg Watrud Construction, LLC for Improvement Project 20-07 New Public Works.
Purpose/Background:
Resolution and Pay Estimate #1 attached.
Funding Source:
Funding for this this item was budgeted as part of the public works building project.
Recommendation:
RJM Construction, our construction management consultant, has inspected the completed work and recommends approving partial payment #1 in the amount of $2,503.25 to Steenberg Watrud Construction, LLC for Improvement Project #20-07, New Public Works Facility.
Action:
Motion to adopt Resolution #20-276 authorizing partial payment #1 to Steenberg Watrud Construction, LLC for Improvement Project #20-07, New Public Works Facility.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | Grant Riemer | 11/19/2020 08:44 AM |
| Kurt Ulrich | Kurt Ulrich | 11/19/2020 03:19 PM |
- Form Started By:
- MaryJo Warner
- Started On:
- 11/19/2020 08:19 AM
- Final Approval Date:
- 11/19/2020