5.16.
CC Regular Session
- Meeting Date:
- 01/12/2021
- Submitted For:
- Bruce Westby
- By:
- Joe Feriancek, Engineering/Public Works
Information
Title
Adopt Resolution #21-011 Ordering Plans and Specifications for Improvement Project # 21-04, 2021 Neighborhood Pavement Overlay Improvements.
Purpose/Background:
Purpose:
The purpose of this case is to adopt Resolution #21-011 Ordering Plans and Specifications for Improvement Project #21-04 2021 Neighborhood Pavement Overlay Improvements.
Background:
Overlaying the streets identified within the 2021 – 2030 Capital Improvement Program for 2021 will allow the City to maintain these streets in the most cost-effective manner throughout the serviceable life of the streets.
Exhibits are attached showing the specific street segments proposed to receive bituminous pavement overlay improvements in 2021. These street segments are located in the following developments:
A street segment summary is attached, the proposed project is 1.81 miles in total length.
The proposed improvements are designated as City Improvement Project #21-04, 2021 Neighborhood Pavement Overlay Improvements.
The purpose of this case is to adopt Resolution #21-011 Ordering Plans and Specifications for Improvement Project #21-04 2021 Neighborhood Pavement Overlay Improvements.
Background:
Overlaying the streets identified within the 2021 – 2030 Capital Improvement Program for 2021 will allow the City to maintain these streets in the most cost-effective manner throughout the serviceable life of the streets.
Exhibits are attached showing the specific street segments proposed to receive bituminous pavement overlay improvements in 2021. These street segments are located in the following developments:
- Birch Hill Lodges
- Ferrum 1st & 2nd
- Gateway Industrial Park
- Mallard Ponds
- Northfork Itasca Point
- Northfork St. Andrews
- Oakridge Industrial Park
- Rabbit Run
- Ramsey Meadows 2nd
A street segment summary is attached, the proposed project is 1.81 miles in total length.
The proposed improvements are designated as City Improvement Project #21-04, 2021 Neighborhood Pavement Overlay Improvements.
Notification:
No notifications are required with this case.
Observations/Alternatives:
Motion to adopt Resolution #21-011 ordering plans and specifications for improvement project #21-04, 2021 Neighborhood Pavement Overlay Improvements.
Funding Source:
Funding for this improvement is proposed to come from the Pavement Management Fund and Stormwater Utility Fund.
Staff has completed an estimate based on anticipated 2021 construction cost, with a total estimated project cost of $690,000.
Staff has completed an estimate based on anticipated 2021 construction cost, with a total estimated project cost of $690,000.
- Street Project Cost $643,000
- Storm Sewer Project Cost $47,000
- Total Estimated Project Cost $690,000
Recommendation:
Staff recommends adopting Resolution #21-011 ordering plans and specifications for improvement project #21-04, 2021 Neighborhood Pavement Overlay Improvements.
Action:
Adopt Resolution #21-011 ordering plans and specifications for improvement project #21-04, 2021 Neighborhood Pavement Overlay Improvements.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Kurt Ulrich | Kathy Schmitz | 01/07/2021 11:00 AM |
| Kurt Ulrich | Kathy Schmitz | 01/07/2021 01:43 PM |
| Bruce Westby | Bruce Westby | 01/07/2021 02:22 PM |
- Form Started By:
- Joe Feriancek
- Started On:
- 12/31/2020 10:59 AM
- Final Approval Date:
- 01/07/2021