5.10.
CC Regular Session
- Meeting Date:
- 01/26/2021
- Submitted For:
- Bruce Westby
- By:
- Marsha Weidner, Engineering/Public Works
Information
Title
Adopt Resolution #21-029 Authorizing Final Payment to Northern Lines Contracting, Inc. for Improvement Project 18-09, COR Infiltration Basin Improvements.
Purpose/Background:
Resolution and Pay Request Attached.
Observations/Alternatives:
Issuing final payment will be contingent on receipt of the following items from Northern Lines Contracting, Inc.:
- IC 134 (Contractor's Withholding Affidavit showing compliance with the provisions of Minnesota Statute 290.92 requiring withholding state income tax).
- Waiver of Mechanic's Lien Rights (Affidavits that all claims against Northern Lines Contracting, Inc. by reasons of the contract have been fully paid or satisfactorily secured).
- Consent of Surety to final Payment (Certification from the contractor's surety)
Recommendation:
The Engineering Technician IV has inspected the completed work and recommends final payment to Northern Lines Contracting, Inc. for Improvement Project #18-09, COR Infiltration Basin Improvements, in the amount of $105,341.94.
Action:
Motion to adopt Resolution #21-029 Authorizing Final Payment to Northern Lines Contracting, Inc. for Improvement Project #18-09, COR Infiltration Basin Improvements, in the amount of $105,341.94.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 01/21/2021 03:30 PM |
| Kurt Ulrich | Kurt Ulrich | 01/21/2021 03:32 PM |
- Form Started By:
- Marsha Weidner
- Started On:
- 01/13/2021 11:39 AM
- Final Approval Date:
- 01/21/2021