5.2.
Public Works Committee
- Meeting Date:
- 09/21/2021
- Submitted For:
- Grant Riemer
- By:
- Grant Riemer, Engineering/Public Works
Title:
Update on Street Light Request for Bear Park
Purpose/Background:
Purpose:
The purpose of this case is to update the Public Works Committee of the street light request for Bear Park.
Background: At the July Public Works Committee meeting, staff brought forward a request for a street light at Bear Park that was received from a resident in the area. At that meeting the committee requested that we poll the residents in the area to gather their input on the street light.
The purpose of this case is to update the Public Works Committee of the street light request for Bear Park.
Background: At the July Public Works Committee meeting, staff brought forward a request for a street light at Bear Park that was received from a resident in the area. At that meeting the committee requested that we poll the residents in the area to gather their input on the street light.
Timeframe:
5 minutes
Observations/Alternatives:
Staff received two emails in favor of the street light installation and those emails are attached to the case.
Funding Source:
Cost of installing the street light would be $ 4,893.00, with an ongoing monthly maintenance and energy cost of $6.76. These funds would come from the street light utility fund GL code 9603
Recommendation:
Staff recommends installing a street light at 15500 Roanoke St (Bear Park) as requested by the residents in that area.
Action:
Motion to committee to accept staff recommendation and move forward with install a street light at 15500 Roanoke St (Bear Park)
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Kurt Ulrich | Kurt Ulrich | 09/16/2021 02:37 PM |
- Form Started By:
- Grant Riemer
- Started On:
- 09/03/2021 03:02 PM
- Final Approval Date:
- 09/16/2021