Adopt Resolution #21-297 Authorizing Partial Payment #13 to RJM Construction for Improvement Project 20-07 New Public Works Facility
Purpose/Background:
Resolution and Pay Estimate #13 attached.
Observations/Alternatives:
Checks are made payable and addressed to contractors, payments will be sent to RJM Construction, LLC for disbursement as listed in the attached Resolution #21-297.
Funding Source:
Funding for this this item was budgeted as part of the public works building project.
Recommendation:
The Public Works Superintendent has inspected the completed work and recommends approving partial payment #13 in the amount of $813,125.66 to RJM Construction for Improvement Project #20-07, New Public Works Facility.
Action:
Motion to adopt Resolution #21-297 authorizing partial payment #13 to RJM Construction for Improvement Project #20-07, New Public Works Facility.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | Kathy Schmitz | 10/21/2021 11:37 AM |
| Kurt Ulrich | Kurt Ulrich | 10/21/2021 02:12 PM |
- Form Started By:
- MaryJo Warner
- Started On:
- 10/18/2021 08:28 AM
- Final Approval Date:
- 10/21/2021