5.14.
CC Regular Session
- Meeting Date:
- 11/23/2021
- By:
- MaryJo Warner, Engineering/Public Works
Information
Title
Adopt Resolution #21-320 Authorizing Partial Payment #14 to RJM Construction for Improvement Project 20-07 New Public Works Facility
Purpose/Background:
Resolution and Pay Estimate #14 attached
Observations/Alternatives:
Checks are made payable and addressed to contractors, payments will be sent to RJM Construction, LLC for disbursement as listed in the attached Resolution #21-320.
Funding Source:
Funding for this this item was budgeted as part of the public works building project.
Recommendation:
The Public Works Superintendent has inspected the completed work and recommends approving partial payment #14 in the amount of $155,453.65 to RJM Construction for Improvement Project #20-07, New Public Works Facility.
Action:
Motion to adopt Resolution #21-320 authorizing partial payment #14 to RJM Construction for Improvement Project #20-07, New Public Works Facility.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | MaryJo Warner | 11/12/2021 02:07 PM |
| Kurt Ulrich | Kurt Ulrich | 11/17/2021 01:10 PM |
- Form Started By:
- MaryJo Warner
- Started On:
- 11/08/2021 12:56 PM
- Final Approval Date:
- 11/17/2021