Information

Title

Adopt Resolution #22-022 Authorizing Final Payment to North Valley Inc. for Improvement Project #21-02, Tiger Street Reconstruction.

Purpose/Background:

Resolution and Pay Request Attached.

Observations/Alternatives:

Issuing final payment will be contingent on receipt of the following items from North Valley, Inc.:

1. IC 134 (Contractor’s Withholding Affidavit showing compliance with the provisions of Minnesota Statute 290.92 requiring withholding state income tax)
2. Waiver of Mechanic’s Lien Rights (Affidavits that all claims against North Valley, Inc. by reasons of the contract have been fully paid or satisfactorily secured)
3. Consent of Surety to Final Payment (Certification from the contractor’s surety)

Following receipt of these items, final payment will be issued.

Recommendation:

The Engineer Technician IV has inspected the completed work and recommends authorizing final payment to North Valley, Inc. of Nowthen, Minnesota for Improvement Project #21-02, Tiger Street Reconstruction, in the amount of $12,695.11.

Action:

Motion to adopt Resolution #22-022 Authorizing Final Payment to North Valley, Inc. of Nowthen, Minnesota for Improvement Project #21-02, Tiger Street Reconstruction, in the amount of $12,695.11. 

Attachments

Form Review

Inbox Reviewed By Date
Bruce Westby Bruce Westby 02/16/2022 02:25 PM
Kurt Ulrich Kurt Ulrich 02/17/2022 09:53 AM
Form Started By:
Marsha Weidner
Started On:
02/07/2022 01:50 PM
Final Approval Date:
02/17/2022