5.13.
CC Regular Session
- Meeting Date:
- 02/22/2022
- Submitted For:
- Bruce Westby
- By:
- Marsha Weidner, Engineering/Public Works
Information
Title
Adopt Resolution #22-035 Authorizing Final Payment to North Valley Inc. for Improvement Project #21-03, Business Park 95 Street Reconstruction.
Purpose/Background:
Resolution and Pay Request Attached.
Observations/Alternatives:
Issuing final payment will be contingent on receipt of the following items from North Valley, Inc.:
- IC 134 (Contractor's Withholding Affidavit showing compliance with the provisions of Minnesota Statute 290.92 requiring withholding state income tax).
- Waiver of Mechanic's Lien Rights (Affidavits that all claims against North Valley, Inc. by reasons of the contract have been fully paid or satisfactorily secured).
- Consent of Surety to final payment (Certification from the contractor's Surety).
Recommendation:
The Engineer Technician IV has inspected the completed work and recommends final payment to North Valley, Inc. of Nowthen, Minnesota, for Improvement Project #21-03, Business Park 95 Street Reconstruction, in the amount of $56,630.68.
Action:
Motion to adopt Resolution #22-035 Authorizing Final Payment to North Valley Inc. of Nowthen, Minnesota for Improvement Project #21-03, Business Park 95 Street Reconstruction, in the amount of $56,630.68.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Bruce Westby | 02/16/2022 02:28 PM |
| Kurt Ulrich | Kurt Ulrich | 02/17/2022 10:16 AM |
- Form Started By:
- Marsha Weidner
- Started On:
- 02/15/2022 01:24 PM
- Final Approval Date:
- 02/17/2022