Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
  • Sunwood Drive & Waco Street Reconstructions (IP #22-01)
    • Plans are being prepared in-house
    • Waco Street remains as is per City Council direction
    • Council to consider approving plans and authorizing bids March 22nd
  • Autumn Heights Street Reconstructions (IP #22-02)
    • Plans are being prepared in-house
    • Council to consider approving plans and authorizing bids at future meeting
  • 2022 MSA Pavement Overlay Improvements (IP #22-03)
    • Plans are being prepared in-house
    • Council to consider approving plans and authorizing bids at future meeting
  • 2022 Neighborhood Street Overlay Improvements (IP #22-04)
    • Plans are being prepared in-house
    • Council to consider approving plans and authorizing bids March 22nd
  • Riverdale Drive Trunk Utility Improvements (IP #22-05)
    • Bolton & Menk prepared plans and specs
    • Bids opened March 11th – Staff will provide an update during the meeting
  • Wood Pond Hills 2nd, 3rd, 4th, 5th Addns Street Reconstructions (IP #22-06)
    • Plans are being prepared in-house
    • Council to consider approving plans and authorizing bids March 22nd
  • 2022 Crack Seal Improvements (IP #22-08)
    • Plans are being prepared in-house
    • Council to consider approving plans and authorizing bids March 22nd
  • WTP Trunk Watermain Improvements (#21-08)
    • First bids rejected
    • Revising plans to reduce project costs
    • Re-bid revised plans in 2022 or early 2023
    • September 2023 completion deadline
  • Centralized Water Treatment Plant (#21-09)
    • AE2S is preparing plans and handling construction administration
    • 60-percent plans nearly complete
    • Project completion anticipated October 2023
  • Fire Station No. 1 Parking Lot Improvements (#21-10)
    • Awarded to North Valley for spring/summer 2022 construction
  • Ramsey Gateway Highway 10 Improvements (IP #20-11)
    • Preliminary design complete and property acquisitions underway
    • Final design underway
    • Construction anticipated late 2023 – early 2026
  • Wetland 114P Outlet Control Improvements (#19-07)
    • Requested by Minnesota DNR
    • Council will consider approving plans and authorizing bids April 12
    • Construction proposed for 2022
 
Anoka County Improvement Projects
  • Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive
    • Anoka County received $1.35M in HSIP funds (est. project cost = $1.5M)
    • Anoka County and City of Ramsey share $150,000 each (per $1.5M est.)
    • Anoka County/WSB preparing plans
    • Construction proposed for 2023, pending City & County approvals
    • Council will consider approving JPA in May 2022
  • CSAH 116 Interim Improvements
    • Construction substantially complete
    • Sunwood Dr. & Bunker Lake Blvd. signal system operational
 
MnDOT Improvement Projects
  • US 10 / 169 & Ferry Street / TH 47 Interchange
    • Construction proposed for 2022 – 2023
  • Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
    • Preliminary design on hold
    • MnDOT exploring realignment of Highway 47 to remove S-curve
    • $45M in bonds authorized October 2020
    • Construction proposed for 2024 or later
  • Rum River Bridge Replacement
    • Construction scheduled for 2022 – 2023
    • Proposing three lanes each direction between Highway 47 and 7th Street
 
Studies & Items of Interest
  • 5805 148th Lane NW
    • Update anticipated March 2022
  • FYA Improvements at Sunwood Drive and Ramsey Boulevard
    • SEH completing Feasibility Analysis
  • Elk River Highway 10 Study
    • Update anticipated March 2022
  • Anoka Solution Highway 10 Improvements
    • Construction scheduled for 2022 – 2023   
  • Water Efficiency Grant Update
    • See attached financials
    • Council will consider approving application for 2022-2024 Grant March 22   

Timeframe:

Staff estimates up to 10 minutes will be needed for updates and discussion.  

Observations/Alternatives:

N/A

Funding Source:

N/A

Recommendation:

N/A

Action:

No formal action required.  For Committee review and discussion purposes only.  

Attachments

Form Review

Inbox Reviewed By Date
Grant Riemer MaryJo Warner 03/10/2022 04:00 PM
Kurt Ulrich Kurt Ulrich 03/10/2022 04:35 PM
Form Started By:
Bruce Westby
Started On:
03/07/2022 04:07 PM
Final Approval Date:
03/10/2022