5.13.
CC Regular Session
- Meeting Date:
- 03/22/2022
- Submitted For:
- Joe Feriancek
- By:
- Joe Feriancek, Engineering/Public Works
Information
Title
Adopt Resolution #22-073 Approving Plans and Specifications and Authorizing Advertisement for Bids for Sunwood Drive and Waco Street Reconstruction, Improvement Project #22-01
Purpose/Background:
Purpose:
The purpose of this case is to adopt resolution #22-073 Approving Plans and Specifications and Authorizing Advertisement for Bids for Sunwood Drive and Waco Street Reconstruction, Improvement Project #22-01.
Background:
City Improvement Project 22-01 proposes to reconstruct Sunwood Drive between Trunk Highway 47 and Waco Street, and Waco Street between Sunwood Drive and 150th Avenue. The streets total approximately 2,500 lineal feet (0.48 miles) in length, and are 44 feet wide as measured to the face of curb.
Project History
Pavement History
Sunwood Drive and Waco Street were constructed in 1985 and 1992 respectively. Pavement maintenance has included crack seal / seal coat improvements in 1992 (Sunwood Drive), 2006, 2013. Maintenance crews have performed patching over the last several years, including extensive spray patching. No pavement overlay improvements have been performed on these street segments. 2021 PASER values were 3 for Sunwood Drive and 3 for Waco Street.
Ground Penetrating Radar (GPR) was performed on the street segments. Bituminous pavement thickness was found to have an average thickness of 4.20 inches on Sunwood Drive and 3.9 inches on Waco Street. GPR was not able to reliably identify the aggregate base thickness, however, the soil borings performed as part of the geotechnical report found an average of 6.4 inches.
Proposed Improvements
Sunwood Drive and Waco Street are Municipal State Aid (MSA) streets, and must comply with State Aid design requirements. MSA design requires these to be a 10-ton design. Based on the traffic counts performed in 2021 (1,800 ADT Sunwood, 580 ADT Waco), the required pavement section is 5” aggregate base and 4” bituminous pavement.
Staff review found the existing pedestrian ramps within the project area did not meet current ADA requirements, therefore all seven pedestrian ramps will need to be removed and replaced. The concrete curb and gutter were found to generally be in good condition, and only spot repairs are proposed. Staff is proposing minimal impacts to the existing bituminous trail with the project beyond what is required for matching into the new pedestrian ramps. The south leg of trail at the intersection of Sunwood Drive and Trunk Highway 47 is proposed to be straightened, the current 90-degree corner is a hazard for plowing.
Review of the sanitary sewer and watermain did not find issues requiring repair. The City will be placing inflow and infiltration barriers on the sanitary sewer manholes with this project. The City received an MCES I/I Grant for this work, which will reimburse the City for the costs associated with the I/I barriers.
Televising of the storm sewer system found more issues than anticipated, and will require removal and replacement of six storm sewer structures and their connecting pipes. The majority of this work will be concentrated at the intersection of Sunwood Drive and Zuni Street.
The current pavement marking layout meets State Aid standard, and the road is proposed to be marked back to the existing layout.
Generally, impacts to boulevards will be minor, just as necessary for removal and replacement of concrete curb and gutter, pedestrian ramp improvements, and excavation required for the storm sewer repairs.
Anticipated Build Process
Preliminary Schedule Remaining
State Aid Approval
Plans are currently being routed through State Aid for approval, which is required before the project can be bid. Staff does not anticipate significant comments from State Aid which would require moving the proposed project bid opening.
Staff proposes to open bids on April 18, 2022, and to present the bid results to City Council on April 26, 2022 for award of a construction contract to the lowest responsible bidder.
Final plans are not attached to this case to prevent potential bidders from downloading plans attached to the case to prepare and submit their bids, rather than purchasing the plans through QuestCDN, the electronic bidding software used by the City of Ramsey. This ensures all bidders are bidding off the same set of plans, and all bidders are notified of any plan revisions (addenda) issued during the bidding process. Attached is the title sheet from the plans showing the scope of the improvements, as well as a plan sheet showing the typical sections, which includes information on the proposed pavement section. Plans are available upon request from the City Engineer.
The purpose of this case is to adopt resolution #22-073 Approving Plans and Specifications and Authorizing Advertisement for Bids for Sunwood Drive and Waco Street Reconstruction, Improvement Project #22-01.
Background:
City Improvement Project 22-01 proposes to reconstruct Sunwood Drive between Trunk Highway 47 and Waco Street, and Waco Street between Sunwood Drive and 150th Avenue. The streets total approximately 2,500 lineal feet (0.48 miles) in length, and are 44 feet wide as measured to the face of curb.
Project History
- 2022 – 2031 Capital Improvement Program – listed as street reconstruction for 2022
- Resolution #21-194, adopted July 13, 2021; City Council ordered the City Engineer to request proposals for Topographic Survey, Geotechnical Evaluations and Utility Testing for 2022 Pavement Management Program projects.
- Resolution #21-224, adopted August 10, 2021; City Council awarded a proposal to Hakanson Anderson for Topographic Survey, and Haugo Geotechnical Services for a geotechnical report of the project area.
- Resolution #21-240, adopted August 24, 2021; City Council awarded a proposal to Hydro-Klean, LLC for cleaning and televising the sanitary sewer and storm sewer, and Water Conservation Services, Inc. for watermain leak testing of the project area.
- October 19, 2021; Public Works Committee gave City Staff direction to review the option of reducing the width of Waco Street within the project area from 46 feet to 34 feet as measured from the back of curb.
- Resolution #21-299, adopted October 26, 2021; City Council ordered the City Engineer to prepare plans and specifications for the improvement project.
- Resolution #21-345, adopted December 14, 2021; City Council approved reconstruction Waco Street to the existing pavement width as part of the improvement project. Staff review had found the estimated life cycle cost savings to have a significant shortfall to the initial costs.
- March 15, 2022; Public Works Committee gave recommendation for City Council approving plans and specifications and authorizing advertisement for bids for Sunwood Drive and Waco Street Reconstruction, Improvement Project #22-01
Pavement History
Sunwood Drive and Waco Street were constructed in 1985 and 1992 respectively. Pavement maintenance has included crack seal / seal coat improvements in 1992 (Sunwood Drive), 2006, 2013. Maintenance crews have performed patching over the last several years, including extensive spray patching. No pavement overlay improvements have been performed on these street segments. 2021 PASER values were 3 for Sunwood Drive and 3 for Waco Street.
Ground Penetrating Radar (GPR) was performed on the street segments. Bituminous pavement thickness was found to have an average thickness of 4.20 inches on Sunwood Drive and 3.9 inches on Waco Street. GPR was not able to reliably identify the aggregate base thickness, however, the soil borings performed as part of the geotechnical report found an average of 6.4 inches.
Proposed Improvements
Sunwood Drive and Waco Street are Municipal State Aid (MSA) streets, and must comply with State Aid design requirements. MSA design requires these to be a 10-ton design. Based on the traffic counts performed in 2021 (1,800 ADT Sunwood, 580 ADT Waco), the required pavement section is 5” aggregate base and 4” bituminous pavement.
Staff review found the existing pedestrian ramps within the project area did not meet current ADA requirements, therefore all seven pedestrian ramps will need to be removed and replaced. The concrete curb and gutter were found to generally be in good condition, and only spot repairs are proposed. Staff is proposing minimal impacts to the existing bituminous trail with the project beyond what is required for matching into the new pedestrian ramps. The south leg of trail at the intersection of Sunwood Drive and Trunk Highway 47 is proposed to be straightened, the current 90-degree corner is a hazard for plowing.
Review of the sanitary sewer and watermain did not find issues requiring repair. The City will be placing inflow and infiltration barriers on the sanitary sewer manholes with this project. The City received an MCES I/I Grant for this work, which will reimburse the City for the costs associated with the I/I barriers.
Televising of the storm sewer system found more issues than anticipated, and will require removal and replacement of six storm sewer structures and their connecting pipes. The majority of this work will be concentrated at the intersection of Sunwood Drive and Zuni Street.
The current pavement marking layout meets State Aid standard, and the road is proposed to be marked back to the existing layout.
Generally, impacts to boulevards will be minor, just as necessary for removal and replacement of concrete curb and gutter, pedestrian ramp improvements, and excavation required for the storm sewer repairs.
Anticipated Build Process
- Install traffic control measures
- These are maintained throughout the project
- Layout of traffic control may be adjusted to accommodate construction periodically
- Install erosion control measures
- Full-depth reclamation of existing bituminous pavement and aggregate base
- Storm sewer repairs
- Project removals (spot curb and gutter, pedestrian ramps, driveways as needed)
- Place new concrete curb and gutter and pedestrian ramps (5 to 7-day cure time)
- Remove excess reclaim material, shape and compact 5 inches of remaining material
- Excess reclaim is stockpiled and will be used on future City projects
- Place first lift of new bituminous pavement
- Finish any trail and driveway repairs
- Restore the boulevard in any impacted areas
- 4 inches topsoil, seed and hydro-mulch
- Place the final lift of new bituminous pavement
- Remove traffic control measures as allowed
- Place all pavement marking, must wait 72 hours after paving
- Erosion control measures are removed after restoration has been completed
Preliminary Schedule Remaining
- Council Approves Plans and Specifications / Authorizes Ad for Bids
- March 22, 2022
- Staff Receives Bids
- April 18, 2022
- Council Awards Contract to the lowest responsible bidder
- April 26, 2022
- Contractor begins construction
- June 2022
- Contractor Substantially Completes construction
- September 2, 2022
- Contractor Final Completion (project clean up, punch list created)
- September 30, 2022
State Aid Approval
Plans are currently being routed through State Aid for approval, which is required before the project can be bid. Staff does not anticipate significant comments from State Aid which would require moving the proposed project bid opening.
Staff proposes to open bids on April 18, 2022, and to present the bid results to City Council on April 26, 2022 for award of a construction contract to the lowest responsible bidder.
Final plans are not attached to this case to prevent potential bidders from downloading plans attached to the case to prepare and submit their bids, rather than purchasing the plans through QuestCDN, the electronic bidding software used by the City of Ramsey. This ensures all bidders are bidding off the same set of plans, and all bidders are notified of any plan revisions (addenda) issued during the bidding process. Attached is the title sheet from the plans showing the scope of the improvements, as well as a plan sheet showing the typical sections, which includes information on the proposed pavement section. Plans are available upon request from the City Engineer.
Notification:
If Council approves plans and specifications and authorizes advertising for bids, bids will be advertised on Friday, March 25, and again on Friday, April 1, 2022, both in the City’s official newspaper, the Anoka Union Herald, and in Finance & Commerce.
Additionally, letters will be mailed to property owners with updates on the project status. Engineering Staff maintains City Improvement webpages with the most current project information, this can be found on the City website, Engineering department page.
Additionally, letters will be mailed to property owners with updates on the project status. Engineering Staff maintains City Improvement webpages with the most current project information, this can be found on the City website, Engineering department page.
Observations/Alternatives:
Motion to adopt Resolution #22-073 approving plans and specifications and authorizing advertisement for bids for Sunwood Drive and Waco Street Reconstruction, Improvement Project #22-01.
Funding Source:
Funding for this improvement is proposed to come from MSA Funds, Stormwater Utility Funds, and Sanitary Sewer Utility Funds.
Staff has completed an estimate based on the final plans and anticipated 2022 construction costs, with a total estimated project cost of $572,160.33, which includes 23-percent indirect costs for administrative, engineering, finance, and legal costs.
Staff has completed an estimate based on the final plans and anticipated 2022 construction costs, with a total estimated project cost of $572,160.33, which includes 23-percent indirect costs for administrative, engineering, finance, and legal costs.
- Street Construction Costs $391,163.00
- Storm Sewer Costs $66,808.00
- Sanitary Sewer Costs $7,200.00
- Indirect Costs $106,989.33
- Total Estimated Project Costs $572,160.33
Recommendation:
Staff recommends adopting Resolution #22-073 approving plans and specifications and authorizing advertisement for bids for Sunwood Drive and Waco Street Reconstruction, Improvement Project #22-01.
The Public Works Committee reviewed the Sunwood Drive and Waco Street Reconstruction project on March 15, 2022 and recommended the City Council approve the plans and authorize advertisements for bids.
The Public Works Committee reviewed the Sunwood Drive and Waco Street Reconstruction project on March 15, 2022 and recommended the City Council approve the plans and authorize advertisements for bids.
Action:
Adopt Resolution #22-073 approving plans and specifications and authorizing advertisements for bids for Sunwood Drive and Waco Street Reconstruction, Improvement Project #22-01
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Bruce Westby | Joe Feriancek | 03/16/2022 11:08 AM |
| Bruce Westby | Bruce Westby | 03/17/2022 01:58 PM |
| Kurt Ulrich | Kurt Ulrich | 03/17/2022 03:58 PM |
- Form Started By:
- Joe Feriancek
- Started On:
- 03/15/2022 08:09 AM
- Final Approval Date:
- 03/17/2022