6.1.
Public Works Committee
Meeting Date:
04/19/2022
By:
Bruce Westby, Engineering/Public Works

Title:

Receive Updates on Improvement Projects, Studies and Items of Interest.

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
  • Sunwood Drive & Waco Street Reconstructions (IP #22-01)
    • Plans were prepared in-house
    • Bids will be opened May 2, 2022
    • Council will consider awarding a construction contract May 10, 2022
  • Autumn Heights Street Reconstructions (IP #22-02)
    • Plans are being prepared in-house
    • Council to consider approving plans and authorizing bids at future meeting
  • 2022 MSA Pavement Overlay Improvements (IP #22-03)
    • Plans are being prepared in-house
    • Council to consider approving plans and authorizing bids at future meeting
  • 2022 Neighborhood Street Overlay Improvements (IP #22-04)
    • Plans are being prepared in-house
    • Bids will be opened May 2, 2022
    • Council will consider awarding a construction contract May 10, 2022
  • Riverdale Drive Trunk Utility Improvements (IP #22-05)
    • Change Order #1 approved April 12, 2022
    • Under construction
  • Wood Pond Hills 2nd, 3rd, 4th, 5th Street Reconstructions (IP #22-06)
    • Plans were prepared in-house
    • Bids will be opened May 2, 2022
    • Council will consider awarding a construction contract May 10, 2022
  • 2022 Crack Seal Improvements (IP #22-08)
    • Plans were prepared in-house
    • Bids will be opened May 2, 2022
    • Council will consider awarding a construction contract May 10, 2022
  • WTP Trunk Watermain Improvements (#21-08)
    • First bids rejected
    • Revising plans to reduce project costs
    • Re-bid revised plans in 2022 or early 2023
    • September 2023 completion deadline
  • Centralized Water Treatment Plant (#21-09)
    • AE2S is preparing plans and handling construction administration
    • 60-percent plans under review
    • Project completion anticipated October 2023
  • Fire Station No. 1 Parking Lot Improvements (#21-10)
    • 2022 construction project
  • Ramsey Gateway Highway 10 Improvements (IP #20-11)
    • Preliminary design complete
    • Final design underway and property acquisitions in progress
    • Construction anticipated late 2023 through early 2026
  • Wetland 114P Outlet Control Improvements (#19-07)
    • Requested by Minnesota DNR
    • Staff is preparing plans
    • Construction proposed for 2023
 
City of Anoka Improvement Projects  
Anoka County Improvement Projects
  • Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive (IP #23-03)
    • Anoka County received $1.35M in HSIP funds (est. project cost = $1.5M)
    • Anoka County and City of Ramsey share $150,000 each (per $1.5M est.)
    • Anoka County/WSB preparing plans
    • Construction proposed for 2023, pending City & County approvals
    • Council will consider approving JPA in April/May 2022
 
MnDOT Improvement Projects
  • Anoka Solution Highway 10 Improvements
    • Construction underway with completion proposed in Spring 2024
  • US 10 / 169 & Ferry Street / TH 47 Interchange
    • Construction underway with completion proposed in Spring 2024
  • Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
    • Preliminary design on hold
    • MnDOT exploring realignment of Highway 47 to remove S-curve
    • $45M in bonds authorized October 2020
    • Construction proposed for 2024 or later
  • Rum River Bridge Replacement
    • Construction underway with completion proposed in Spring 2024
    • Proposing three lanes each direction between Highway 47 and 7th Street
 
Studies & Items of Interest
  • 5805 148th Lane NW
    • No updates at this time.  Property owners like everything as is.
  • FYA Improvements at Sunwood Drive and Ramsey Boulevard
    • Staff will inform Anoka County that the City does not want to construct FYA improvements following Council approval of the March PWC minutes.
  • Elk River Highway 10 Corridor Study
    • Update anticipated May 2022

Timeframe:

Staff estimates up to 15 minutes will be needed for updates and discussion.  

Observations/Alternatives:

N/A

Funding Source:

N/A

Recommendation:

Staff does not have any recommendations to offer on these topics at this time. 

Action:

No formal action required. For Committee review and discussion purposes only.  

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Grant Riemer Grant Riemer 04/14/2022 02:47 PM
Kurt Ulrich MaryJo Warner 04/14/2022 04:30 PM
Form Started By:
Bruce Westby
Started On:
04/14/2022 11:09 AM
Final Approval Date:
04/14/2022