6.1.
Public Works Committee
- Meeting Date:
- 06/21/2022
- By:
- Bruce Westby, Engineering/Public Works
Title:
Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
City of Anoka Improvement Projects
Anoka County Improvement Projects
MnDOT Improvement Projects
Studies & Items of Interest
City Improvement Projects
- Sunwood Drive & Waco Street Reconstructions (IP #22-01)
- Contract awarded to Novco, Inc. May 24, 2022
- Contract execution in progress
- Autumn Heights Street Reconstructions (IP #22-02)
- Plans were prepared in-house
- Council to consider approving plans and authorizing bids June 28, 2022
- 2022 Neighborhood Street Overlay Improvements (IP #22-04)
- Contract awarded to North Valley, Inc. May 10, 2022
- Pre-construction meeting held June 8, 2022
- Construction in progress
- Riverdale Drive Trunk Utility Improvements (IP #22-05)
- Construction in progress – sanitary sewer lift station
- Construction proposed for completion by end of July 2022
- Wood Pond Hills 2nd, 3rd, 4th, 5th Street Reconstructions (IP #22-06)
- Contract awarded to North Valley, Inc. May 10, 2022
- Pre-construction meeting held June 8, 2022
- Construction proposed to begin mid-July 2022
- 2022 Crack Seal Improvements (IP #22-08)
- Construction completed
- 2022 Pavement Rejuvenation Improvements (IP #22-09)
- Construction proposed to begin mid-July 2022
- 2022 MSA Pavement Striping Improvements (IP #22-13)
- Plans are being prepared in-house
- Council to consider approving plans & authorizing quotes July 12, 2022
- 15410 Argon Street Drainage Improvements (IP #22-14)
- See case on June 21, 2022 PWC agenda for details
- Council to consider authorizing plans and specifications June 28, 2022
- WTP Trunk Watermain Improvements (#21-08)
- First bids rejected
- Plans will be revised to minimize project costs without sacrificing quality, and to include necessary WTP commissioning improvements (well-house valves, etc.).
- Council to consider revised contract with SEH, Inc. July 2022
- Council to consider re-bidding revised plans August/September 2022
- April 2024 completion deadline
- Centralized Water Treatment Plant (#21-09)
- AE2S is preparing plans and handling construction administration
- 90-percent plans to be submitted for Staff review soon
- Project completion proposed by Spring 2024 (before water use increases)
- Fire Station No. 1 Parking Lot Improvements (#21-10)
- Construction in progress
- Ramsey Gateway Highway 10 Improvements (IP #20-11)
- Final design and property acquisitions in progress
- Bolton & Menk is preparing plans and specifications
- 60-percent plans to be submitted for Staff review soon
- Construction anticipated Fall 2023 through early 2026 (2024/25 majority)
- Council to consider potential City-led project to advance construct Riverdale Drive east of Sunfish Lake Boulevard in Spring/Summer 2023 during the City Council Work Session June 28, 2022
- Riverdale Drive Extension – Llama Street to Bowers Drive (IP #20-05)
- Plans are complete and in for final review and approval by MnDOT State Aid
- Council to consider approving plans and authorizing bids June 28, 2022
- Construction proposed for completion by October 2022
- Wetland 114P Outlet Control Improvements (#19-07)
- Requested by Minnesota DNR
- Staff is preparing plans, including boardwalk reconstruction
- Construction proposed for 2023
City of Anoka Improvement Projects
- Highway 47 Corridor Improvements
- Construction proposed for 2025
- Anoka webpage https://clients.bolton-menk.com/anokahwy47/
Anoka County Improvement Projects
- Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive (IP #23-03)
- Anoka County received $1.35M in HSIP funds (est. project cost $1.5M)
- Council approved JPA May 24, 2022 (City cost share = $28,667.64)
- Construction proposed for 2023, pending final City & County approvals
MnDOT Improvement Projects
- Anoka Solution Highway 10 Improvements
- Construction underway with completion proposed in Spring 2024
- Anoka webpage https://clients.bolton-menk.com/hwy10/
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
- US 10 / 169 & Ferry Street / TH 47 Interchange
- Construction underway with completion proposed in Spring 2024
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
- Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
- Preliminary design suspended to explore s-curve realignment
- $45M in bonds authorized October 2020
- Construction proposed for 2024 (or later)
- A public Open House was held on May 25 (handouts attached)
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy47rr-anoka/
- Rum River Bridge Replacement
- Construction underway with completion proposed in Spring 2024
- Proposing three lanes each direction between Highway 47 and 7th Street
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
Studies & Items of Interest
- 5805 148th Lane NW
- No updates at this time. Property owners like everything as is.
- Elk River Highway 10 Corridor Study
- Staff will provide a detailed update at the meeting
- Study website https://www.highway10corridorstudy.com/
- A copy of the final report is available on the study website
Timeframe:
Staff estimates up to 20 minutes will be needed for updates and discussion.
Observations/Alternatives:
N/A
Funding Source:
N/A
Recommendation:
Staff does not have recommendations to offer on these topics at this time.
Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Grant Riemer | Grant Riemer | 06/16/2022 10:31 AM |
| Brian Hagen | Brian Hagen | 06/16/2022 02:54 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 06/16/2022 05:27 AM
- Final Approval Date:
- 06/16/2022