6.1.
Public Works Committee
- Meeting Date:
- 09/20/2022
- By:
- Bruce Westby, Engineering/Public Works
Title:
Receive Updates on Improvement Projects, Studies and Items of Interest
Purpose/Background:
The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.
City Improvement Projects
City of Anoka Improvement Projects
Anoka County Improvement Projects
MnDOT Improvement Projects
Studies & Items of Interest
City Improvement Projects
- 161st Avenue Reconstruction (IP #23-01)
- Staff is preparing plans and specifications
- Coordinating design and plans with PACT Charter school
- 2023 construction proposed
- Staff proposes to construct Central Park parking lot improvements separately
- 167th Avenue Reconstruction (IP #23-04)
- Staff is preparing plans and specifications
- Evaluating regional trail alignment and crossings
- 2023 construction proposed
- Sunwood Drive & Waco Street Reconstructions (IP #22-01)
- Construction in progress
- Construction must be complete by September 30th
- Autumn Heights Street Reconstructions (IP #22-02)
- Preconstruction meeting was conducted September 16th
- Substantial completion is required by October 31st
- 2022 Neighborhood Street Overlay Improvements (IP #22-04)
- Construction in progress
- Construction must be complete by September 30th
- Riverdale Drive Trunk Utility Improvements (IP #22-05)
- Construction in progress
- Sanitary sewer lift station almost complete
- Wood Pond Hills 2nd, 3rd, 4th, 5th Street Reconstructions (IP #22-06)
- Construction in progress
- Construction must be complete by September 30th
- 2022 MSA Pavement Striping Improvements (IP #22-13)
- Construction in progress
- 15410 Argon Street Drainage Improvements (IP #22-14)
- Staff plans to present proposals to City Council October 11th
- Highway 47 Sound Wall north of Xkimo Street (IP #22-17)
- Staff plans to request PWC action in October/November
- WTP Trunk Watermain Improvements (#21-08)
- Plans are being revised to minimize project costs and to include WTP commissioning improvements (well-house valves, etc.).
- Staff will request Council authorization to advertise bids when material prices decline
- Centralized Water Treatment Plant (#21-09)
- 100-percent plans are complete
- Staff will request Council authorization to advertise bids when material prices decline
- Ramsey Gateway Highway 10 Improvements (IP #20-11)
- Final design / property acquisitions underway
- Bolton & Menk preparing 95-percent plans and specifications
- Construction anticipated Fall 2023 through early 2026 (2024 - 2025 majority)
- Riverdale Drive Extension – Llama Street to Bowers Drive (IP #20-05)
- Substantial completion proposed September 30th
- Final completion proposed October 31st
- Wetland 114P Outlet Control Improvements (#19-07)
- Requested by Minnesota DNR
- Staff is preparing plans, including boardwalk reconstruction
- Construction proposed for winter 2022/2023
City of Anoka Improvement Projects
- Highway 47 Corridor Improvements
- Construction proposed for 2025
- Anoka webpage https://clients.bolton-menk.com/anokahwy47/
Anoka County Improvement Projects
- Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive (IP #23-03)
- Anoka County received $1.35M in HSIP funds (est. project cost $1.5M)
- Council approved JPA May 24th with City cost share = $28,667.64
- Construction proposed for 2023, pending final City & County approvals
MnDOT Improvement Projects
- Anoka Solution Highway 10 Improvements
- Construction in progress
- Final completion proposed for Spring 2024
- Anoka webpage https://clients.bolton-menk.com/hwy10/
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
- US 10 / 169 & Ferry Street / TH 47 Interchange
- Construction in progress with completion proposed in Spring 2024
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
- Ferry Street / Trunk Highway 47 Grade Separation @ BNSF Rail Crossing
- Preliminary design suspended to explore s-curve realignment
- $45M in bonds authorized October 2020
- Construction proposed for 2024 or later
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy47rr-anoka/
- Rum River Bridge Replacement
- Construction in progress with completion proposed in Spring 2024
- Proposing three lanes each direction between Highway 47 and 7th Street
- MnDOT webpage http://www.dot.state.mn.us/metro/projects/hwy10-anoka/
Studies & Items of Interest
- 5805 148th Lane NW
- No updates. Property owners are content as is.
- Sunfish Lake Sedimentation Basin Improvements
- Property owner is still interested in pursuing their request.
- Staff will delineate rear property line this Fall as time allows.
- Staff anticipates presenting an update to the PWC this Fall.
- Update on Boulevard Trees for Sunwood Drive (Mark Riverblood)
- Emerald Ash Borer Impacts within the City (Mark Riverblood)
- Update on PMP project revisions in 2023 - 2032 Capital Improvement Plan
- CSAH 5 / Nowthen Boulevard Corridor Study
- Final report will be reviewed with PWC in Fall 2022
- Elk River Highway 10 Corridor Study
- Study website https://www.highway10corridorstudy.com/
- Open House - Thursday, September 22nd, 3:30 – 7 PM, Elk River City Hall
- Final report will be reviewed with PWC when complete (Fall 2022?)
Timeframe:
Staff estimates up to 45 minutes will be needed for updates and discussion.
Observations/Alternatives:
Staff does not have recommendations to offer on these topics at this time.
Funding Source:
N/A
Recommendation:
Staff does not have recommendations to offer on these topics at this time.
Action:
No formal action required. For Committee review and discussion purposes only.
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Brian Hagen | Brian Hagen | 09/15/2022 03:00 PM |
- Form Started By:
- Bruce Westby
- Started On:
- 09/15/2022 08:09 AM
- Final Approval Date:
- 09/15/2022