Skip to main content

AgendaQuick™

View Agenda Item

5.16.
CC Regular Session
Meeting Date:
11/22/2022
By:
Bruce Westby, Engineering/Public Works

Information

Title

Adopt Resolution #22-270 Approving Proposal from Bolton and Menk, Inc. to Prepare Plans and Specifications for Improvement Project #23-04, 167th Avenue Reconstruction 

Purpose/Background:

City Improvement Project 23-04 proposes to reconstruct 167th Avenue between Nowthen Boulevard (CSAH 5) and Saint Francis Boulevard (TH 47). This street segment is approximately 6,000 feet (1.13 miles) in length, and the width varies between 40-feet on the westerly rural section (0.97 miles) and 48-feet (0.16 miles) on the easterly urban section. A full shoulder/parking lane exists on both sides of this street segment.
 
This segment of 167th Avenue is a Municipal State Aid (MSA) street, and must be designed to MSA standards, including a 10-ton pavement design. Staff proposes to generally leave the street at its current widths and elevations. A figure showing the project scope is included in Bolton & Menk, Inc’s professional services proposal attached to this case.
 
Attached are previous City Council cases with the adopted Resolutions pertaining to this project including;
  • Case #13323, Resolution #22-130 (June 14, 2022) - City Council accepted a proposal from Bolton & Menk, Inc. or topographic survey from Bolton & Menk, Inc.
  • Case #13546, Resolution #22-201 (August 23, 2022) - Council authorized a contract with Haugo Geotechnical Services for geotechnical evaluations
  • Case #13534, Resolution #22-204 (August 23, 2022) - Council ordered the City Engineer to prepare plans and specifications
 
Due to City Council’s current efforts to increase funding for the City’s Pavement Management Program (PMP) by $12 million dollars, Staff requests Council approval of the attached professional services proposal from Bolton and Menk, Inc. to prepare final plans and specifications and administer the bid process for Improvement Project #23-04 at a not-to-exceed fee of $121,405.  These costs are proposed to be paid for as indirect project costs using the City’s State Aid funds. Contracting with Bolton and Menk, Inc. to prepare final plans and specifications for this project will allow Engineering Staff to prepare plans and specifications for the remaining 2023 PMP projects in-house.   

Recommendation:

Staff recommends adopting Resolution #22-270.  

Action:

Adopt Resolution #22-270 approving the proposal from Bolton and Menk, Inc. to prepare plans and specifications for Improvement Project #23-04, 167th Avenue Reconstruction.   

Attachments

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 11/17/2022 03:56 PM
Form Started By:
Bruce Westby
Started On:
11/15/2022 07:49 AM
Final Approval Date:
11/17/2022