Receive Updates on Improvement Projects, Studies and Items of Interest

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
  • 161st Avenue Reconstruction (IP #23-01)
    • Staff is preparing plans and specifications
    • Staff is coordinating design with PACT Charter school
    • Staff applied for ATIP trail grant funding per Council approval
    • 2023 construction proposed
  • Central Park Parking Lot Reconstruction (IP #23-02)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 167th Avenue Reconstruction (IP #23-04)
    • Bolton & Menk is preparing plans and specs per Council approval
    • Bolton & Menk is evaluating pedestrian facility options
    • Staff applied for ATIP trail grant funding per Council approval
    • 2023 construction proposed
  • Barthels Rum River Acres 2nd Reconstruction (IP #23-05)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 MSA Pavement Overlay Improvements (IP #23-06)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 Neighborhood Pavement Overlay Improvements (IP #23-07)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 Crack Seal Improvements (IP #23-08)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 Pavement Rejuvenator Improvements (IP #23-09)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • Whispering Pines Estates Plat 3 Reconstructions (IP #23-10)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • Trott Brook Crossing Sanitary Sewer Lift Station Improvements (IP #23-11)
    • Bolton and Menk is preparing plans and specifications per Council approval
    • 2023 construction proposed
  • Ferret Street Reconstruction and Utility Improvements (IP #23-12)
    • Bolton and Menk is preparing plans and specifications per EDA approval
    • 2023 construction proposed to support ARAA sports dome project
  • Sunwood Drive & Waco Street Reconstructions (IP #22-01)
    • Construction complete è punch list mode
  • Autumn Heights Street Reconstructions (IP #22-02)
    • Construction complete è punch list mode
  • 2022 Neighborhood Street Overlay Improvements (IP #22-04)
    • Construction complete è punch list mode
  • Riverdale Drive Trunk Utility Improvements (IP #22-05)
    • Construction complete è punch list mode
  • Wood Pond Hills 2nd, 3rd, 4th, 5th Street Reconstructions (IP #22-06)
    • Construction complete è punch list mode
  • 15410 Argon Street Drainage Improvements (IP #22-14)
    • Construction complete è removing from list
  • Highway 47 Sound Wall north of Xkimo Street (IP #22-17)
    • City Council will consider authorizing bids on 01/24/23
  • WTP Trunk Watermain Improvements (#21-08)
    • Plans are being revised to minimize project costs and include WTP commissioning improvements (well-house valves, etc.)
    • City Council will consider authorizing bids when plans are complete
  • Centralized Water Treatment Plant (#21-09)
    • AE2S finalizing plans and specs
    • City Council will consider authorizing bids on 01/24/23  
  • Ramsey Gateway Highway 10 Improvements (IP #20-11)
    • Final design nearly complete
    • Property/easement acquisitions in progress
    • Construction anticipated 2023 through early 2026 (2024 - 2025 majority)
    • Riverdale Drive east of SLB & temp US 10 widening Spring/Summer 2023
  • Riverdale Drive Extension – Llama Street to Bowers Drive (IP #20-05)
    • Construction substantially complete è Hwy 10 improvements still needed
  • Wetland 114P Outlet Control Improvements (#19-07)
    • City Council will consider authorizing bids on 01/24/23
 
City of Anoka Improvement Projects  
Anoka County Improvement Projects
  • Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive (IP #23-03)
    • Anoka County received $1.35M in HSIP funds (est. project cost $1.5M)
    • JPA includes City cost share of $28,667.64
    • Construction proposed for 2023 pending final City & County approvals
 
MnDOT Improvement Projects  
Studies & Items of Interest
  • Sunfish Lake Sedimentation Basin Improvements
    • Property owner interested in pursuing request to fill swale and grade basin
    • Staff delineated rear property line last Fall and notified property owner
    • Staff anticipates presenting an update in February 2023
  • CSAH 5 / Nowthen Boulevard Corridor Study
    • Staff will present the final report when available
  • Elk River Highway 10 Corridor Study

Timeframe:

Staff estimates up to 15 minutes will be needed for updates and discussion.  

Observations/Alternatives:

N/A

Funding Source:

N/A

Recommendation:

N/A

Action:

No formal action required.  For Committee review and discussion purposes only.  

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 01/12/2023 02:17 PM
Form Started By:
Bruce Westby
Started On:
01/11/2023 10:37 AM
Final Approval Date:
01/12/2023