6.1.
Public Works Committee
Meeting Date:
03/21/2023
By:
Bruce Westby, Engineering/Public Works

Title:

Receive Updates on Improvement Projects, Studies and Items of Interest

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
  • 161st Avenue Reconstruction (IP #23-01)
    • Plans and specifications were advertised for bids
    • Coordinating design and project schedule w/ PACT Charter school
    • Staff applied for ATIP trail grant funding per Council approval
    • 2023 construction proposed
  • Central Park Parking Lot Reconstruction (IP #23-02)
    • Staff is preparing plans and specifications
    • Staff is reviewing project schedule options based on current Park reservations
    • 2023 construction proposed, but some/all may occur in 2024
  • 167th Avenue Reconstruction (IP #23-04)
    • Bolton & Menk is preparing plans and specifications
    • Staff applied for ATIP trail grant funding per Council approval
    • 2023 construction proposed
  • Barthels Rum River Acres 2nd Reconstruction (IP #23-05)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 MSA Pavement Overlay Improvements (IP #23-06)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 Neighborhood Pavement Overlay Improvements (IP #23-07)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 Crack Seal Improvements (IP #23-08)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 Pavement Rejuvenator Improvements (IP #23-09)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • Whispering Pines Estates Plat 3 Reconstructions (IP #23-10)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • Trott Brook Crossing Sanitary Sewer Lift Station Improvements (IP #23-11)
    • Bolton and Menk is preparing plans and specifications
    • Coordinating design and project schedule w/ Trott Brook Crossing/TCLD
    • Final completion proposed for Fall 2023
  • HY-10 Ramsey Improvements (IP #23-12)
    • Plans and specifications were advertised for bids
    • 2023 construction proposed to support existing uses and development
  • Highway 47 Sound Wall north of Xkimo Street (IP #22-17)
    • MnDOT is reviewing plans/preparing Cooperative Construction Agreement
    • Staff anticipates requesting Council approval to authorize bids in April
  • WTP Trunk Watermain Improvements (#21-08)
    • Staff anticipates requesting Council approval to amend SEH, Inc. agreement in April to revise plans and remove inspections
    • Staff anticipates requesting council approval to authorize bids Fall 2023
  • Centralized Water Treatment Plant (#21-09)
    • See PWC agenda case  
  • Ramsey Gateway Highway 10 Improvements (IP #20-11)
    • Final design plans approaching 100-percent
    • Property/easement acquisitions nearly complete
    • Executing agreements
    • Construction anticipated mid-2023 through early 2026 (2024 - 2025 majority)
    • Riverdale Drive east of SLB & temp US 10 widening mid 2023
  • Riverdale Drive Extension – Llama Street to Bowers Drive (IP #20-05)
    • Construction substantially complete è Hwy 10 improvements still needed
  • Wetland 114P Outlet Control Improvements (#19-07)
    • Sanitary sewer manhole castings will be raised soon
    • Need DNR Permit to begin grading and outlet control improvements
 
City of Anoka Improvement Projects  
Anoka County Improvement Projects
  • Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive (IP #23-03)
    • Anoka County received $1.35M in HSIP funds (est. project cost $1.5M)
    • JPA includes City cost share of $28,667.64
    • Bids accepted and Contract awarded by Anoka County Board last week
    • Tree clearing anticipated to begin in March
    • 2023 construction
 
MnDOT Improvement Projects  
Studies & Items of Interest
  • Sunfish Lake Sedimentation Basin Improvements
    • Property owner indicated interest in pursuing filling of swale and grading a sedimentation basin
    • Staff delineated rear property line last Fall and notified property owner
    • Staff working to contact property owner
  • CSAH 5 / Nowthen Boulevard Corridor Study
    • Final report will be presented February 21st
  • Elk River Highway 10 Corridor Study

Timeframe:

Staff estimates up to 10 minutes may be needed for updates and discussion.  

Observations/Alternatives:

N/A

Funding Source:

Dependent on discussion.

Recommendation:

N/A

Action:

No formal action required.  For Committee review and discussion purposes only.  

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 03/16/2023 01:48 PM
Form Started By:
Bruce Westby
Started On:
03/15/2023 12:14 PM
Final Approval Date:
03/16/2023