Bruce Westby, Engineering/Public Works

Title:

Receive Updates on Improvement Projects, Studies and Items of Interest 

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
  • 161st Avenue Reconstruction (IP #23-01)
    • Plans and specifications advertised for bids
    • Bid opening 04/19/23
    • Staff is meeting w/ property owners of west pond site on 04/14/23 - Meeting minutes will be attached to this case 04/14/23 as requested on 04/11/23
    • ATIP trail grant funding denied
    • Summer/Fall 2023 construction proposed
  • Central Park Parking Lot Reconstruction (IP #23-02)
    • Staff is preparing plans and specifications
    • Fall 2023 construction proposed (after Game Fair)
  • 167th Avenue Reconstruction (IP #23-04)
    • Bolton & Menk is preparing plans and specifications
    • ATIP trail grant funding denied
    • 2023 construction proposed
  • Barthels Rum River Acres 2nd Reconstruction (IP #23-05)
    • See case on agenda
    • 2023 construction proposed
  • 2023 MSA Pavement Overlay Improvements (IP #23-06)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • 2023 Neighborhood Pavement Overlay Improvements (IP #23-07)
    • Plans and specifications are advertised for bids
    • Bid opening 04/21/23
    • 2023 construction proposed
  • 2023 Crack Seal Improvements (IP #23-08)
    • Contract awarded 04/11/23 to Northwest Asphalt
    • 2023 construction proposed
  • 2023 Pavement Rejuvenator Improvements (IP #23-09)
    • 2023 construction proposed
  • Whispering Pines Estates Plat 3 Reconstructions (IP #23-10)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • (Trott Brook Crossing) Sanitary Sewer Lift Station #10 Improvements (IP #23-11)
    • Bolton and Menk is preparing plans and specifications
    • Coordinating design and project schedule w/ Trott Brook Crossing/TCLD
    • Final completion proposed for Fall 2023
  • HY-10 Ramsey Improvements (IP #23-12)
    • Bids opened 04/13/23 (very competitive)
    • City Council to consider award of contract 04/25/23
    • 2023 construction proposed
  • Highway 47 Sound Wall north of Xkimo Street (IP #22-17)
    • MnDOT is preparing Cooperative Construction Agreement
    • Staff anticipates requesting Council approval to authorize bids 04/25/23
  • WTP Trunk Watermain Improvements (#21-08)
    • Staff anticipates requesting Council approval to amend SEH, Inc. agreement late April/early May to revise plans and remove inspections
    • Staff anticipates requesting council approval to authorize bids Fall 2023
  • Centralized Water Treatment Plant (#21-09)
    • Council awarded contract for construction 03/28/23
    • Preconstruction meeting scheduled for 04/26/23
    • Substantial completion scheduled for 05/01/25 (Final 08/01/25)
  • Ramsey Gateway Highway 10 Improvements (IP #20-11)
    • Final design plans at 100-percent
    • Open Houses held 04/12/23
    • Construction schedule; June 2023 through early 2026 (2024 - 2025 majority)
    • Riverdale Drive east of SLB & temp US 10 widening Summer/Fall 2023
  • Riverdale Drive Extension – Llama Street to Bowers Drive (IP #20-05)
    • Construction substantially complete è Hwy 10 improvements still needed
  • Wetland 114P Outlet Control Improvements (#19-07)
    • Sanitary sewer manhole castings raised
    • DNR Permit issued
    • Grading & outlet control structure work to occur Spring/Summer 2023
 
City of Anoka Improvement Projects  
Anoka County Improvement Projects
  • Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive (IP #23-03)
    • City cost share = $28,667.64 per JPA
    • Contract awarded
    • Construction began late March
    • Armstrong Boulevard will remain open to traffic at all times
    • Alpine Drive will close to traffic either side of Armstrong Boulevard at different times  
    • Construction complete Fall 2023
 
MnDOT Improvement Projects  
Studies & Items of Interest
  • Sunfish Lake Sedimentation Basin Improvements
    • Property owner indicated interest in pursuing filling of swale and grading a sedimentation basin
    • Staff delineated rear property line last Fall and notified property owner
    • Staff is working to contact property owner
  • Elk River Highway 10 Corridor Study

Timeframe:

Staff estimates up to 15 minutes will be needed for updates and discussion.  

Observations/Alternatives:

N/A

Funding Source:

N/A

Recommendation:

N/A

Action:

No formal action required.  For Committee review and discussion purposes only.  

Attachments

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 04/13/2023 04:18 PM
Bruce Westby (Originator) MaryJo Warner 04/19/2023 11:45 AM
Bruce Westby (Originator) MaryJo Warner 04/19/2023 11:46 AM
Form Started By:
Bruce Westby
Started On:
04/12/2023 02:24 PM
Final Approval Date:
04/19/2023