6.1.
Public Works Committee
Meeting Date:
06/20/2023
By:
Bruce Westby, Engineering/Public Works

Title:

Receive Updates on Improvement Projects, Studies and Items of Interest

Purpose/Background:

The purpose of this case is to update the Public Works Committee on current and proposed City, County and MnDOT improvement projects and studies, and on other items of interest to the Committee.

City Improvement Projects
  • 161st Avenue Reconstruction (IP #23-01)
    • Construction in progress
    • Staff continues to work with property owners to address concerns
    • On schedule to allow PACT Charter to open on time
  • Central Park Parking Lot Reconstruction (IP #23-02)
    • Staff is finalizing plans and specifications
    • Fall 2023 construction proposed (after Game Fair)
  • 167th Avenue Reconstruction (IP #23-04)
    • Bolton & Menk is finalizing plans and specifications
    • CC to consider approving plans and authorizing bids June 27th
    • Summer/Fall 2023 construction proposed
  • Barthels Rum River Acres 2nd Reconstruction (IP #23-05)
    • Preconstruction meeting conducted June 14, 2023
    • Construction to occur Summer/Fall 2023
  • 2023 MSA Pavement Overlay Improvements (IP #23-06)
    • Staff is preparing plans and specifications
    • Summer 2023 construction proposed
  • 2023 Neighborhood Pavement Overlay Improvements (IP #23-07)
    • Construction in progress
  • 2023 Crack Seal Improvements (IP #23-08)
    • Construction is complete
  • 2023 Pavement Rejuvenator Improvements (IP #23-09)
    • Summer 2023 construction proposed
  • Whispering Pines Estates Plat 3 Reconstructions (IP #23-10)
    • Staff is preparing plans and specifications
    • 2023 construction proposed
  • Trott Brook Crossing Sanitary Sewer Lift Station Improvements (IP #23-11)
    • Construction in progress
    • Fall 2023 final completion
  • HY-10 Ramsey Improvements (IP #23-12)
    • Preconstruction meeting conducted June 14, 2023
    • Summer/Fall 2023 construction
  • Highway 47 Sound Wall north of Xkimo Street (IP #22-17)
    • MnDOT Cooperative Construction Agreement or City to acquire ROW
    • Staff anticipates requesting Council approval to authorize bids Summer 2023
  • WTP Trunk Watermain Improvements (#21-08)
    • Staff anticipates requesting Council approval to amend SEH, Inc. agreement to revise plans and remove inspections July 2023
    • Staff anticipates requesting Council approval of plans and authorization to re-bid Fall 2023
  • Centralized Water Treatment Plant (#21-09)
    • Construction in progress
    • Substantial completion scheduled for May 1, 2025
    • Final completion scheduled for August 1, 2025
  • Ramsey Gateway Highway 10 Improvements (IP #20-11)
    • Construction schedule; June 2023 through early 2026 (2024 - 2025 majority)
    • Riverdale Drive east of SLB & temp US 10 widening Summer/Fall 2023
  • Riverdale Drive Extension – Llama Street to Bowers Drive (IP #20-05)
    • Construction is complete
    • Punch list work in progress
  • Wetland 114P Outlet Control Improvements (#19-07)
    • Construction is complete
    • Punch list work in progress

 City of Anoka Improvement Projects
  • Highway 47 Corridor Improvements
    • 3-lane design proposed south of Bunker Lake Boulevard
    • City just received regional solicitation funds for 2027 construction
    • Signal system at McKinley Street is proposed to be permanent
    • Anoka webpage https://clients.bolton-menk.com/anokahwy47/

Anoka County Improvement Projects
  • Roundabout at Armstrong Boulevard/CSAH 83 and Alpine Drive (IP #23-03)
    • Construction in progress
    • Armstrong Boulevard will remain open to traffic at all times
    • Alpine Drive is closed to traffic either side of Armstrong Boulevard. 
    • Construction complete Fall 2023

MnDOT Improvement Projects
Studies & Items of Interest
  • Sunfish Lake Sedimentation Basin Improvements
    • Property owner indicated interest in filling swale and grading sedimentation basin
    • Staff delineated rear property line last Fall and notified property owner
    • Staff continues working to contact property owner
  • Elk River Highway 10 Corridor Study

Timeframe:

Staff estimates up to 10 minutes will be needed for updates and discussion.  

Observations/Alternatives:

N/A

Funding Source:

N/A

Recommendation:

N/A

Action:

No formal action required. For Committee review and discussion purposes only.  

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Brian Hagen Brian Hagen 06/15/2023 04:12 PM
Form Started By:
Bruce Westby
Started On:
06/15/2023 09:16 AM
Final Approval Date:
06/15/2023